COMPLETE QUESTIONS AND CORRECT
ANSWERS
◉ Construction Management
Answer: The organizing, scheduling, mobilizing and directing
equipment, material and personnel in the performance of
construction.
Managing the construction delivery process and the control of key
factors to ensure the client receives a facility that matches scope and
quality expectations; delivered on time and within budget.
◉ Value Engineering
Answer: Is a process that considers cost in the context of numerous
factors: life cycle cost, quality, durability, and maintainability. Two or
more of these factors must be considered at the same time for an
alternative to be VE.
◉ Cost Reduction
Answer: Is a process that considers cost only when making similar
decisions on life cycle, quality, durability, and maintainability.
◉ Project Procurement
,Answer: Finding and purchasing of the materials called for in the
contract documents and the hiring of contractors/ subcontractors to
build the project.
◉ Traditional Delivery Method
Answer: Architect assists the owner with requests for bid and
related bid packages.
◉ Subcontractor
Answer: A contract issued to a "C" licensed contractor to perform
labor, material and equipment.
◉ Purchase Orders
Answer: A contract issed to a supplier for materials or equipment.
◉ Patent Defect
Answer: Responsible for all items to continue to function flawlessly
for a period of 1 year. Contract must correct items not in compliance.
◉ Latent Defect
Answer: Responsible for all defectively installed work for a period of
10 years from project completion.
, ◉ Construction Documents
Answer: Translate the owners needs in the form of detail text and
graphics to enable contractors with the opportunity to successfully
furnish and install the scope of work required for complete and
proper installation per the contract.
Anything not included in the construction documents are not the
responsibility of the contractor bidding and contracting fro the
work.
◉ Bid Documents
Answer: Invitation to bid
Instructions to bidders
Bid form
◉ Contract Requirements
Answer: Contract
General and supplementary conditions of the contract
◉ Technical Requirements
Answer: Specifications
Plans
Addendums