Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

North American Electric Reliability Corporation Balancing Authority Certification EXAM LATEST QUESTIONS AND 100- Verified ANSWERS

Beoordeling
-
Verkocht
-
Pagina's
34
Cijfer
A+
Geüpload op
25-05-2026
Geschreven in
2025/2026

North American Electric Reliability Corporation Balancing Authority Certification EXAM LATEST QUESTIONS AND 100- Verified ANSWERS

Instelling
Electrical
Vak
Electrical

Voorbeeld van de inhoud

North American Electric Reliability Corporation Balancing
Authority Certification EXAM LATEST 2026-2027 100
QUESTIONS AND 100% Verified ANSWERS
What is the most important information needed for forecasting load?



Planned generation outages

Historic load

Weather forecast

Planned transmission outages - answer>>Weather forecast



When coordinating under frequency load shedding and under frequency generator tripping the
_____________________________.



breakers should open at the same time as the UFLS

generators should trip before the UFLS

load should not be shed during the process

generators should trip after the UFLS - answer>>EOP-011, Emergency Operations - The Transmission Operator and
the Balancing Authority shall have Operating Plans with provisions for operator-controlled manual Load shedding
that minimizes implemented in a timeframe adequate for mitigating the Emergency. Under frequency load
shedding, or UFLS, is designed to drop load to match generation. Under frequency generator relays are designed
to protect generators from operating at low frequencies for an extended period of time. These generator relays
should be set to trip to protect the generators if UFLS is unable to return the frequency to an acceptable value
within a set period of time. The first trip of under frequency generator relays should be AFTER the last trip of UFLS
relays. generators should trip after the UFLS



What is the most important consideration in load forecasting?



Weather

Historic load

Generator outages

,Energy Profile - answer>>Weather



In an island, what is the most appropriate AGC mode of operationConstant Interchange or Flat Tie

Off

Tie-line bias control

Constant or Flat Frequency - answer>>Normally, the Tie Line Bias control mode, which compares the Net Actual
Interchange to the Net Scheduled Interchange plus the Balancing Authority's frequency bias obligation, should be
used. However if a Balancing Authority is operating asynchronously (separated from the Interconnection), it
should switch to Flat Frequency Control since its tie lines are no longer connected to the Interconnection. It is
important for the Balancing Authority to maintain 60 Hz. In the Flat Frequency control mode, ACE is looking only at
the system frequency, not the Interchange portion of the ACE equation.



150 MW is flowing into the high side of a 200 MVA transformer. If the transformer windings have a 2 to 1 ratio
what MW value is flowing out of the low side winding of the transformer?



150 MW

75 MW

250 MW

200 MW - answer>>Power flow through a transformer is constant. The transformer steps up or down the voltage,
but power flow does not change. 150 MW



After a major disturbance, Interconnection frequency is remaining around 59.92Hz, your Balancing Authorities ACE
is 0 and have 200 MW of extra generation. What should the Balancing Authority system operator do?



Offer assistance to entities needing it.

Change the AGC mode to Flat Frequency

Shed Load.

Increase Generation. - answer>>After a disturbance where frequency declines significantly, the entire
Interconnection will react (automatically) with governors increasing generation and load decreasing slightly. Load
and Generation will rebalance at a lower frequency until generation is increased to return the Interconnection
frequency to 60.00 Hz. The best answer is to offer assistance to the deficient Balancing Authority by offering the
200 MW of reserves in a bilateral interchange transaction to help restore generation and load balance in the
Interconnection

,Offer assistance to entities needing it.



Incorrect The load in Balancing Authority "A" is currently 2000 MWs. The Interconnection frequency drops from
60.00 Hz to 59.70 Hz due to a disturbance in another Balancing Authority. What change in load can BA "A" expect
to see?



The load should increase approximately 40 MWs.

The load should decrease approximately 40 MWs.

The load should decrease approximately 20 MWs.

The load should increase approximately 20 MWs. limits - answer>>Load on the power system changes with
frequency. For every 1% change in frequency, load will change approximately 2% in the same direction. This load
change is primarily from induction motor load and not from resistive loads. -

In this scenario, the frequency dropped from 60.00 to 59.70, or .3 Hz. .3 Hz is .5% of 60 Hz. Therefore, load should
decrease 1%, or 20 MWs.



NERC Frequency Response Characteristic Survey Training Document



NERC Standard BAL-003

The load should decrease approximately 20 MWs.



Balancing Authority A expecting a 5,000 MW peak at Hour Ending 1500 hour, when 3,000 MWs of the 7,500 MW
of generation trips. That leaves 4,500 MWs of generation and 1,500 MW purchases to meet the peak demand.
When the purchases are cut by 1,000 MW to a new Net of -500 MW. Total of 5,000 MW in generation and firm
schedule to meet a forecasted 5,000 MW peak load. A factor to consider is a 5,000 MW forecast will most likely
result in a higher instantaneous load and that there is NO generation available for reserves. A Balancing Authority
in this situation would be in an Energy Emergency Alert Level 2 and will work with the Reliability Coordinator to
implement mitigating actions, such as, demand side management.

1.Notify the RC that this BA is contacting TOPs and LSE's to shed 200 MW of load.

2.Notify the RC that this BA is in EEA Level 1; notify all power plants to be on alert.

Notify the RC that this BA is in EEA Lev - answer>>Notify the RC that this BA is in an EEA Level 2; start all available
generation; schedule emergency interchange purchases; prepare to reduce firm load.

, During a system emergency, the System Operator can direct other Transmission Operators and Balancing
Authorities to violate which limit?



Interconnection Reliability Operating Limit

System Operating Limit

Available Transfer Capacity

Equipment parameters should be maintained within their established limits - answer>>Throughout the NERC
Standards requirements state that System Operating Limits must be respected. To ensure a reliable power system,
established limits can not be violated.



Application Equipment parameters should be maintained within their established limits



A simple power system is composed of three transmission lines that connect the generation area to the load area.
The three lines are different lengths but each line has the same impedance. Each line is initially loaded at 200 MW.
The SOL of each line is 400 MW. If one of the three lines trips, what will be the loading on the shortest remaining
line and will the SOL of either remaining line be violated?



300 MW/No

300 MW/Yes

400 MW/Yes

400 MW/No - answer>>300 MW/No NERC Standard TOP-001: Transmission Operators should not operate outside
identified limits and they shall ensure that a Real-time assessment is performed at least once every 30 minutes. In
this scenario, there is a total of 600 MW moving from generation to load across three lines with equal impedance.
When one of the three lines trips, the two remaining lines will each carry 1/2 of the total MW flow, or 300 MW.
The SOL of 400 MW will not be violated.



A request for a generator unit outage has been made to the planners. The planners must analyze this request to



ensure the generator will not be needed

ensure adequate real and reactive reserves

ensure system reliability

Geschreven voor

Instelling
Electrical
Vak
Electrical

Documentinformatie

Geüpload op
25 mei 2026
Aantal pagina's
34
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$19.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
dennohz2000 Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
336
Lid sinds
2 jaar
Aantal volgers
47
Documenten
7417
Laatst verkocht
16 uur geleden

3.9

78 beoordelingen

5
43
4
10
3
11
2
4
1
10

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen