Which stage includes modifications, performance, payments, and
contract closeout? - ANSWER: contract administration stage
The purpose of the Contracting Subway Map is to - ANSWER: provide
the user with a generalized order of events in the acquisition contracting
process
1. What affects how we effectively motivate contractors through the life
cycle? -
ANSWER: governments business strategies
What are the 3 phases of the contracting lifecycle? - ANSWER: 1)
Preaward
2) Award
3) Post-award
,2|Page
When contemplating the business strategy of a procurement, what
should the acquisition team consider when aligning the strategy to
contractor motivations? - ANSWER: - type of contract
- length of contract
- financing arrangement
- profit/fee percentages
- performance evaluation
- data rights
- required warranties
- maintenance/sustainment
- future requirements
5 Stages of the contracting life cycle - ANSWER: -Acquisition planning
-solicitation
-evaluation
-award
-contract administration
What is the overall role of the contracting professional? - ANSWER:
Serve as the overall business advisor to the acquisition team. They are
responsible for guiding the customer through the contracting life cycle
stages.
,3|Page
What type of authority does a contracting officer hold in government
contracting? -
ANSWER: Expressed actual authority
What are the 2 stages in the Pre-Award phase of the contracting life
cycle? - ANSWER: 1) Acquisition Planning Stage
2) Solicitation Stage
What are the 2 stages in the Award phase of the contracting life cycle? -
ANSWER: 1) Evaluation Stage
2) Award Stage
What is the only stage of the Post-Award phase of the contracting life
cycle? - ANSWER: 1) Contract Administration Stage
List the four essential elements of a contract for it to be considered
valid.
- ANSWER: 1) Capacity
2) Mutual Assent
3) Consideration
4) Lawful Purpose
, 4|Page
What are the two preferred methods for determining a fair and
reasonable price? - ANSWER: - Comparison of proposed prices
received in response to the solicitation
- Comparison of previously proposed prices and previous Government
and commercial contract prices with current proposed prices for like
items
Where do we find information on TINA? - ANSWER: FAR 15.403-4
When must the government promote competition in solicitations? -
ANSWER: Unless an exception applies or otherwise is expressly stated
authorized by statute, contracting officers must promote and provide for
full and open competition in soliciting offers and awarding government
contracts.
What are the seven exceptions to competition? - ANSWER: 1) Only
one responsible source and no other supplies or service will satisfy
agency requirements
2) Unusual and compelling urgency
3) Industrial mobilization; engineering, developmental, or research
capability; or expert services