2026 Questions with 100% Correct Answers
A lump sum contract on a project has a total contract price of $160,000. Retainage has been held back at
10%. The contractor has received progress payments for 75% of the project. The contractor submits a
request for final payment for the new completed project. The final payment amount should be for... -
✔✔More than $50,000
What is the total value of current assets for an accrual basis company that has the following? Checking
account cash balance is $4,800; materials inventory for work-in-progress is $4,200; a pick-up truck that
cost $12,460- paid for with $2,460 in cash and a note for $10,000- and is used 100% in the business;
accounts receivable is $5,700; suppliers' accounts payable is $6,300; other accounts payable is $2,200;
and quarterly income tax payment due is $1,180... - ✔✔Between $12,000 and $16,000
What is the total project overhead for a project that lasts 3 months and has the following costs? Labor is
$4,000; materials are $9,500; equipment rentals are $1,200; superintendent's annual salary is $36,000;
office rent is $800 per month; and office utilities are $375 per month. - ✔✔Less than $12,000
For 1 month a company bills out $38,000 in completed work, and receives $22,000 in payments plus
$8,000 from the previous month's billings. They pay their total bill of $26,000 to supply houses for this
month's purchases, and another $5,000 to supply houses for last month's purchases. Using a cash
accounting method and NOT considering any other revenue or expenses, what is the company's net
income for the month? - ✔✔Loss of $1,000
The owner requests for change which will cost the contractor $15,000 in labor and materials and $2,250
in overhead costs. With the change, the contractor would be relieved of $18,000 in labor and materials
costs, and $2,400 in overhead costs from the original contract. The original bid included profit of 20% of
all costs. The contractor wants to make a profit of 20% of all costs on the changes. The adjusted contract
price for the change order should be... - ✔✔A decrease of $3,780
Which of the following would typically be covered by a contractor's comprehensive general liability
insurance policy? - ✔✔Damage to adjoining property from a crane accident
What is the total gross compensation and employment status for a carpenter, given the following
information? A contractor hires a carpenter to do the finish work for a 10-home project. The carpenter is