Domain 1: Acquisition Fundamentals
1. In the Federal Government context, what does the term “acquisition”
refer to?
A. The process of hiring new employees.
B. The purchase or lease of supplies or services, by contract, for
government use.
C. The review of private-sector proposals only.
D. The awarding of grants to non-profit organisations.
Correct ,,,,answer,,,: B.
Rationale: Acquisition is defined as the purchase or lease of supplies and
services, by contract, for use by the Federal Government. It is broader
than just procurement and includes planning, solicitation, and contract
management.
2. Which of the following best defines the Federal Acquisition Regulation
(FAR)?
A. A collection of agency-specific policies for acquisition.
B. A set of rules governing only military acquisitions.
C. A unified body of rules that governs all Federal government
,acquisitions.
D. A legal code for contractor employment rights.
Correct ,,,,answer,,,: C.
Rationale: The FAR is the principal set of regulations governing the
acquisition process for all Federal agencies, ensuring uniformity,
transparency, and fairness.
3. Who is primarily responsible for overseeing the performance of a
contract and ensuring compliance with its terms?
A. The Project Manager (PM).
B. The Contracting Officer’s Representative (COR).
C. The Acquisition Team Leader.
D. The Evaluation Committee.
Correct ,,,,answer,,,: B.
Rationale: The COR is designated to monitor contractor performance and
verify that goods and services are delivered as specified. They act as the
“eyes and ears” of the Contracting Officer (CO).
4. According to the FAR, what is the primary purpose of the acquisition
planning process?
A. To determine the need for supplies and services and plan their
acquisition.
B. To write a statement of work.
C. To award a contract as quickly as possible.
D. To evaluate past contractor performance.
Correct ,,,,answer,,,: A.
Rationale: Acquisition planning is the process of determining the need for
supplies and services and planning the acquisition of those supplies and
services.
5. Which document describes the work to be performed under a contract?
A. Evaluation Criteria.
,B. Acquisition Plan.
C. Statement of Work (SOW).
D. Solicitation Notice.
Correct ,,,,answer,,,: C.
Rationale: The SOW defines the scope of work, tasks, deliverables, and
performance standards required under the contract.
6. What is the purpose of a marketplace analysis during the acquisition
process?
A. To determine government budget levels.
B. To identify potential offerors and evaluate their capabilities.
C. To forecast future acquisition needs only.
D. To verify compliance with FAR requirements.
Correct ,,,,answer,,,: B.
Rationale: Market research and analysis help contracting officers
understand industry capabilities, availability of products/services, and
ensure competition.
7. Which of the following statements best describes the role of the
Contracting Officer (CO)?
A. The CO is responsible for all technical decisions on a contract.
B. The CO is the only person with the authority to bind the government on
a contract.
C. The CO is responsible for inspecting all deliverables.
D. The CO is a member of the contractor’s management team.
Correct ,,,,answer,,,: B.
Rationale: The CO is the only person with the authority to enter into,
administer, or terminate contracts and make related determinations and
findings. No other individual can bind the government contractually.
8. The acquisition team is composed of various members. Who is typically
responsible for managing the budget and funding for an acquisition?
, A. The Contracting Officer (CO).
B. The Resource Advisor or Budget Analyst.
C. The Legal Advisor.
D. The Small Business Specialist.
Correct ,,,,answer,,,: B.
Rationale: The Resource Advisor or Budget Analyst is responsible for
ensuring that funds are available, properly allocated, and aligned with the
acquisition strategy.
9. According to the Competition in Contracting Act (CICA), what is
required for all government acquisitions?
A. Full and open competition to the maximum extent practicable.
B. A sole-source award to a preferred vendor.
C. An acquisition plan approved by Congress.
D. A statement of work written by the contractor.
Correct ,,,,answer,,,: A.
Rationale: CICA requires that contracting officers promote and provide
for full and open competition in their acquisitions unless an exception
applies.
10. Which phase of the project lifecycle involves creating the product or
solution and evaluating whether the outcome meets project objectives?
A. Concept Planning.
B. Development.
C. Implementation.
D. Closeout.
Correct ,,,,answer,,,: B.
Rationale: The Development phase follows the project plan, focusing on
creating the product or solution and evaluating whether the outcome
meets project objectives.
Domain 2: Pre-Award Planning
Answers 2026 Update;Defense
Acquisition University
Domain 1: Acquisition Fundamentals
1. In the Federal Government context, what does the term “acquisition”
refer to?
A. The process of hiring new employees.
B. The purchase or lease of supplies or services, by contract, for
government use.
C. The review of private-sector proposals only.
D. The awarding of grants to non-profit organisations.
Correct ,,,,answer,,,: B.
Rationale: Acquisition is defined as the purchase or lease of supplies and
services, by contract, for use by the Federal Government. It is broader
than just procurement and includes planning, solicitation, and contract
management.
2. Which of the following best defines the Federal Acquisition Regulation
(FAR)?
A. A collection of agency-specific policies for acquisition.
B. A set of rules governing only military acquisitions.
C. A unified body of rules that governs all Federal government
,acquisitions.
D. A legal code for contractor employment rights.
Correct ,,,,answer,,,: C.
Rationale: The FAR is the principal set of regulations governing the
acquisition process for all Federal agencies, ensuring uniformity,
transparency, and fairness.
3. Who is primarily responsible for overseeing the performance of a
contract and ensuring compliance with its terms?
A. The Project Manager (PM).
B. The Contracting Officer’s Representative (COR).
C. The Acquisition Team Leader.
D. The Evaluation Committee.
Correct ,,,,answer,,,: B.
Rationale: The COR is designated to monitor contractor performance and
verify that goods and services are delivered as specified. They act as the
“eyes and ears” of the Contracting Officer (CO).
4. According to the FAR, what is the primary purpose of the acquisition
planning process?
A. To determine the need for supplies and services and plan their
acquisition.
B. To write a statement of work.
C. To award a contract as quickly as possible.
D. To evaluate past contractor performance.
Correct ,,,,answer,,,: A.
Rationale: Acquisition planning is the process of determining the need for
supplies and services and planning the acquisition of those supplies and
services.
5. Which document describes the work to be performed under a contract?
A. Evaluation Criteria.
,B. Acquisition Plan.
C. Statement of Work (SOW).
D. Solicitation Notice.
Correct ,,,,answer,,,: C.
Rationale: The SOW defines the scope of work, tasks, deliverables, and
performance standards required under the contract.
6. What is the purpose of a marketplace analysis during the acquisition
process?
A. To determine government budget levels.
B. To identify potential offerors and evaluate their capabilities.
C. To forecast future acquisition needs only.
D. To verify compliance with FAR requirements.
Correct ,,,,answer,,,: B.
Rationale: Market research and analysis help contracting officers
understand industry capabilities, availability of products/services, and
ensure competition.
7. Which of the following statements best describes the role of the
Contracting Officer (CO)?
A. The CO is responsible for all technical decisions on a contract.
B. The CO is the only person with the authority to bind the government on
a contract.
C. The CO is responsible for inspecting all deliverables.
D. The CO is a member of the contractor’s management team.
Correct ,,,,answer,,,: B.
Rationale: The CO is the only person with the authority to enter into,
administer, or terminate contracts and make related determinations and
findings. No other individual can bind the government contractually.
8. The acquisition team is composed of various members. Who is typically
responsible for managing the budget and funding for an acquisition?
, A. The Contracting Officer (CO).
B. The Resource Advisor or Budget Analyst.
C. The Legal Advisor.
D. The Small Business Specialist.
Correct ,,,,answer,,,: B.
Rationale: The Resource Advisor or Budget Analyst is responsible for
ensuring that funds are available, properly allocated, and aligned with the
acquisition strategy.
9. According to the Competition in Contracting Act (CICA), what is
required for all government acquisitions?
A. Full and open competition to the maximum extent practicable.
B. A sole-source award to a preferred vendor.
C. An acquisition plan approved by Congress.
D. A statement of work written by the contractor.
Correct ,,,,answer,,,: A.
Rationale: CICA requires that contracting officers promote and provide
for full and open competition in their acquisitions unless an exception
applies.
10. Which phase of the project lifecycle involves creating the product or
solution and evaluating whether the outcome meets project objectives?
A. Concept Planning.
B. Development.
C. Implementation.
D. Closeout.
Correct ,,,,answer,,,: B.
Rationale: The Development phase follows the project plan, focusing on
creating the product or solution and evaluating whether the outcome
meets project objectives.
Domain 2: Pre-Award Planning