LADOTD Structural Concrete Inspection 2 |
questions and answers | latest update| verified !!
ANSWERS QUESTIONS
, equipment, procedures, material Whiat should be discussed at a prepour
Save
supply conference?
the distance between bars, the What should be checked on reinforcing steel
distance from bar ends to side forms, during a prepour inspection?
and the straightness of bars
the anticipated deflection under the What should be considered when establishing the
screen, the finished grade, and the proper elevation of a transverse screed?
rail elevation
to ensure that the screed will yield What is the main purpose of the dry run of the
proper grade at all points transverse screed over the pour unit?
the District Laboratory Engineer Who must approve the PCC Job Mix Release prior
to beginning a pour?
two years How long is a concrete plant certification valid?
Cement Certificate of Delivery What must accompany a shipment of cement that is
to be used in concrete for DOTD projects?
the working face of the stockpiles, Which areas must the contractor take aggregate
and the flow between the batch bin samples from for job control and verification
and the weighing hopper testing?
revolution counters, drum capacity What items should be checked daily on a transit
and rotation speeds, and the mixer?
water metering system
place the bucket on a What is an acceptable procedure for filling a
plywood platform concrete bucket?
questions and answers | latest update| verified !!
ANSWERS QUESTIONS
, equipment, procedures, material Whiat should be discussed at a prepour
Save
supply conference?
the distance between bars, the What should be checked on reinforcing steel
distance from bar ends to side forms, during a prepour inspection?
and the straightness of bars
the anticipated deflection under the What should be considered when establishing the
screen, the finished grade, and the proper elevation of a transverse screed?
rail elevation
to ensure that the screed will yield What is the main purpose of the dry run of the
proper grade at all points transverse screed over the pour unit?
the District Laboratory Engineer Who must approve the PCC Job Mix Release prior
to beginning a pour?
two years How long is a concrete plant certification valid?
Cement Certificate of Delivery What must accompany a shipment of cement that is
to be used in concrete for DOTD projects?
the working face of the stockpiles, Which areas must the contractor take aggregate
and the flow between the batch bin samples from for job control and verification
and the weighing hopper testing?
revolution counters, drum capacity What items should be checked daily on a transit
and rotation speeds, and the mixer?
water metering system
place the bucket on a What is an acceptable procedure for filling a
plywood platform concrete bucket?