TANK NEWEST ACTUAL EXAM WITH COMPLETE
QUESTIONS AND ANSWERS// VERIFIED//GRADED A+//
New owners of an existing UST system shall register
the UST system with DEQ/LARA within what period
from date of ownership?
30 days
UST systems with cathodic protection should be
inspected for proper operation by a qualified cathodic
protection tester on the following schedule:
Every three years
UST systems with impressed current cathodic
protection systems must be inspected at a minimum:
Every 60 days
Statistical Inventory reconciliation (SIR) analyzes the
following as a means of leak detection:
Page 1 of 21
,Inventory, Delivery and Dispensing
Manual tank gauging can be used as the 'sole' means of
a leak detection for tanks that are X gallons or less in
capacity. X is:
550 gallons
Check if the following statement is true or false: "A
third party evaluation of a statistical inventory
reconciliation is good for any type of tank and product."
False
Automatic line leak detectors must be able to detect a
leak of at least X gallons per hour at a line pressure of
10 psi witin one hour. X is:
3 gallons per hour
Line testing of piping shall be capable of detecting X
gallons per hour leak rate at 1 and a half times the
operating pressure. X is:
Page 2 of 21
, 0.1 gallons per hour
What actions are not appropriate when when the
owner/operator becomes aware of a spill or overfill?
Drain the spill to the storm sewer or nearby ditch
Upon confirmation of a release to the
soil/groundwater/surface water the operator shall:
Report the release to the DEQ within 24 hours, by fax or
phone
A Class B operator shall not be responsible for more
than the following facilities:
45 facilities
What is the minimum frequency of site inspections to
assure operational compliance?
Quarterly