Which of the following would represent, or potentially represent, an
organizational conflict of interest (OCI)? - CORRECT ANSWER-An engineering
support contractor (contractor A) is hired to assist in the development of
Government specifications for a new requirement. Contractor A writes the
specifications in such a way as to require the Government's use of contractor A's
proprietary processes even though there are other solutions.
Which term means the total cost to the Government of acquiring, operating,
supporting, and (if applicable) disposing of the items being acquired? -
CORRECT ANSWER-Life-cycle costs
Which of the following reflects market research policy? Market research: -
CORRECT ANSWER-Aids in determining if sources capable of satisfying the
agency's requirements exist
Which section of the uniform contract format (UCF) exists to include negotiated,
meaningful special contract requirements that are not included in Section I,
,Contract clauses, or in other sections of the UCF? - CORRECT ANSWER-Section
H
Who is the individual designated and authorized in writing by the contracting
officer to perform specific technical or administrative functions? - CORRECT
ANSWER-Contracting officer's representative
What phase of acquisition does Market Research take place - CORRECT
ANSWER-All phases of the acquisition
What is the use of a procedure that is inconsistent with the FAR - CORRECT
ANSWER-Deviation
Simplified Acquisition Procedures (SAP) should: - CORRECT ANSWER-Promote
competition to the maximum extent practicable
What is the tool (form) used by DoD to apply a structured profit/fee - CORRECT
ANSWER-DD Form 1547, Weighted Guidelines Method
, What type(s) of contracts can be awarded when acquiring commercial items of
supply? - CORRECT ANSWER-Only firm-fixed-price contracts or fixed-price
contracts with economic price adjustment
When using invitations for bids (IFBs), what type(s) of contracts can be awarded -
CORRECT ANSWER-Only firm-fixed-price contracts or fixed-price contracts
with economic price adjustment
Which of the following is correct regarding the DFARS Procedures Guidance and
Information (PGI)? - CORRECT ANSWER-The DFARS PGI is a companion
resource to the DFARS
Which of the following statements is accurate regarding the Government's policy
on contract modifications? - CORRECT ANSWER-Only contracting officers
acting within the scope of their authority are authorized to execute contract
modifications on behalf of the Government
Which of the following is accurate about unilateral modifications? - CORRECT
ANSWER-Are only signed by a Government contracting officer, not the
contractor
Types of Contracting Officers - CORRECT ANSWER-KO, Admin, Terminating