⩥ What are the 5 aspects of the PRAM?
Answer: Initiate
Identify
Assess
Plan responses
Implement responses
⩥ What are the 5 phases in the extended project life cycle?
Answer: Concept
Definition
Development
Handover and Closure
Operations
⩥ Who are potential stakeholders within a project?
Answer: Project Sponsor
Project Team
,Users
Suppliers
Customers
Senior Management
⩥ What are the 5 steps within the information management
process?
Answer: Collection
Storage
Dissemination
Archiving
Destruction
⩥ What are the steps of the requirements management process?
Answer: Capture
Analyse
Justify
Baseline
⩥ What are the steps of the change control process?
, Answer: - Submit Change Request
- Review viability of taking request further
- Assessment of feasibility and impact of the proposed change
- Decision
⩥ What are potential sources of change?
Answer: Internal:
- Technical Error
- Incorrect Estimate
- Resourcing Issues
External:
- Business Justification
- Requirements change
- Technology/Market Shift
⩥ What is the requirements model?
Answer: Business Need (Why)
Features (How)
Requirements (What)