, TRUE or FALSE? You can pre-assign a service time as an True
attribute before you actually get to the server that you'll
be using.
TRUE or FALSE? If you have Create module generating False
one-at-a-time customer arrivals, then it is not possible to
use a different Create module with 4-at-a-time customer
arrivals.
TRUE or FALSE? Fake customers can be used to schedule True
machine breakdowns, keep track of which time period the
simulation is currently in, and carry out other duties not
associated with actual customers.
Which module/spreadsheet is NOT in the Advanced Process Module. This is in the Basic Process panel.
Process panel?
Why are things like Seize, Delay, Release in multiple The Process module does not allow us to use Seize, Delay, Release with sufficient
templates? generality.
TRUE or FALSE? You can schedule failures to occur after True
a random number of customers have used a resource or
after a random amount of time has passed.
TRUE or FALSE? You are only allowed to schedule one False
type of failure for a particular resource.
Which block is NOT in the Blocks template? Process block. There is no such thing. However, the Process module is in the Basic
Process panel.
TRUE or FALSE? The Queue block can connect up to the False
Seize module from the Advanced Process template.
Which kinds of sets are allowed? Resources set, counter set, entity type set, entity picture set
TRUE or FALSE? It is possible for the resource Joey to be True
a member of three different resource sets.
TRUE or FALSE? For easy display and organizational True
purposes, our Call Center simulation is divided into