Term Definition
A type of organization which C
"loans" resources to projects
while still maintaining control
over them is called
a. Pure project structure
b. Pure functional structure
c. Matrix structure
d. Product structure
Give this one a try later!
True False
2 of 15
Term Definition
, Which statement is true D
regarding activities not on the
critical path?
a. Usually cannot be delayed
b. Have less slack than activities
on the critical path
c. Can delay a project if they are
highly variable
d. Are used to crash project
completion times
Give this one a try later!
True False
Correct definition
C
3 of 15
Term Definition
A project has three paths. A-B-C
D
has a length of 25 days. A-D-C
has a length of 15 days. Finally,
A-E-C has a length of 20 days.
Which one of the following
statements is true?
a. A-D-C is the critical path.
Term Definition
A type of organization which C
"loans" resources to projects
while still maintaining control
over them is called
a. Pure project structure
b. Pure functional structure
c. Matrix structure
d. Product structure
Give this one a try later!
True False
2 of 15
Term Definition
, Which statement is true D
regarding activities not on the
critical path?
a. Usually cannot be delayed
b. Have less slack than activities
on the critical path
c. Can delay a project if they are
highly variable
d. Are used to crash project
completion times
Give this one a try later!
True False
Correct definition
C
3 of 15
Term Definition
A project has three paths. A-B-C
D
has a length of 25 days. A-D-C
has a length of 15 days. Finally,
A-E-C has a length of 20 days.
Which one of the following
statements is true?
a. A-D-C is the critical path.