Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

NICET HIGHWAY CONSTRUCTION INSPECTOR LEVEL III PRACTICE EXAM 1 QUESTIONS & VERIFIED DETAILED SOLUTIONS 100%

Rating
-
Sold
-
Pages
12
Grade
A+
Uploaded on
11-06-2026
Written in
2025/2026

NICET HIGHWAY CONSTRUCTION INSPECTOR LEVEL III PRACTICE EXAM 1 QUESTIONS & VERIFIED DETAILED SOLUTIONS 100% NICET HIGHWAY CONSTRUCTION INSPECTOR LEVEL III PRACTICE EXAM 1 QUESTIONS & VERIFIED DETAILED SOLUTIONS 100%

Institution
NICET I/II/III/IV - National Institute For Certification In Engineering Technologies
Course
NICET I/II/III/IV - National Institute For Certification In Engineering Technologies

Content preview

NICET HIGHWAY CONSTRUCTION
INSPECTOR LEVEL III PRACTICE
EXAM 1 QUESTIONS & VERIFIED
DETAILED SOLUTIONS 100%
During installation of traffic loops in the pavement, which three statements apply prior to
and during the installation of loop wire? (Choose 3).

a) Do not allow vehicular traffic over an open saw cut.
b) Do not overlap saw cuts at the corner.
c) Thoroughly clean the saw cut of foreign material.
d) Use a plastic sleeve where loop wire crosses a joint. - Correct Answer ✔✔ a) Do not
allow vehicular traffic over an open saw cut.
c) Thoroughly clean the saw cut of foreign material.
d) Use a plastic sleeve where loop wire crosses a joint.

The contractor is installing a culvert with a 12-inch reinforced concrete pipe ( outside
diameter of 16.50 inches) from Sta 10+00, 40 feet Left to STA 10+00, 65 feet Right on
4-inch bedding material. The 12-inch RCP outlet is to be installed at Sta 10+00, 40 feet
Left at an invert elevation of 652.50.

If the conduit is installed at a 1.40% slope, what is the elevation of the foundation grade
at Sta 10+00, 45 feet Right?

a) 652.04
b) 653.17
c) 653.36
d) 653.50 - Correct Answer ✔✔ ?

On the reservoir side of a dam, erosion protection against wave action should extend up
the slope to at least which level?

a) crest of dam
b) maximum water elevation
c) minimum water elevation
d) two-thirds the height of the dam - Correct Answer ✔✔ b) maximum water elevation

During stage construction while installing drainage, the contractor must complete which
two of the following tasks? (Choose two).

a) Bulk head the pipe until the system is complete.

, b) Complete the entire system before it rains.
c) Maintain the existing drainage system until the new system is functional.
d) Provide temporary connections as needed to maintain the existing system. - Correct
Answer ✔✔ c) Maintain the existing drainage system until the new system is functional.
d) Provide temporary connections as needed to maintain the existing system.

After flushing but before connecting a new main to the existing system, what test does
an inspector need to verify before placing the main into service?

a) bacteriological testing
b) cover testing
c) deflection testing
d) pressure testing - Correct Answer ✔✔ d) pressure testing

Which three types of inspections are completed for sign structures? (Choose three).

a) final inspection
b) interim inspection
c) initial inspection
d) routine inspection - Correct Answer ✔✔ b) interim inspection
c) initial inspection
d) routine inspection

How many times per foot should loop lead-in wires be twisted?

a) 3 turns per foot
b) 5 turns per foot
c) 6 turns per foot
d) 7 turns per foot - Correct Answer ✔✔ b) 5 turns per foot

Which phrase is true of test reports required for concrete sidewalks, asphalt pavement,
concrete curb, and pipe culverts for rest areas?

a) 50% required on roadway contracts
b) required for federal-aid projects only
c) same as roadway contracts
d) submitted in duplicate - Correct Answer ✔✔ ?

According to FP-14, when removing existing concrete structure in the roadbed, how
many inches below the subgrade elevation should the existing structure be removed to?

a) 12 inches
b) 24 inches
c) 30 inches
d) 36 inches - Correct Answer ✔✔ d) 36 inches

Written for

Institution
NICET I/II/III/IV - National Institute For Certification In Engineering Technologies
Course
NICET I/II/III/IV - National Institute For Certification In Engineering Technologies

Document information

Uploaded on
June 11, 2026
Number of pages
12
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$16.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF


Also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
STUVIA2024 Chamberlain College Nursing
Follow You need to be logged in order to follow users or courses
Sold
21
Member since
1 year
Number of followers
0
Documents
7340
Last sold
1 week ago

5.0

2 reviews

5
2
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions