The plans for the installation of cab walls call for two different size panels. The large panels
require 12 bolts and the small panels require 8 bolts. If each car has 6 large panels and 4 small
panels, how many bolts will be needed? - (answer)104 bolts
Five different pipes have lengths 3 ¼ ft., 4 ⅝ ft., 2 ½ ft., 4 ¾ ft. and 2 5⁄16 ft. What is the total
length of the pipes? - (answer)17 7⁄16 ft.
A 13 ft. I-beam needs to be cut into 4 equal pieces for blocking beams. What should each beam
measure? - (answer)3.25 ft
A salesperson makes 22% commission on their total sales. If one month, the salesperson sold a
total of $45,000 in goods, what is their commission? - (answer)9,900$
How many license plates are possible if each plate number is comprised of two letters followed
by three numbers, where repetition of both numbers and letters is allowed? - (answer)676000
One amp is equal to 6,240,000,000,000,000,000 electrons per second. Write this rate using
scientific notation. - (answer)6.24 x 10 (to the 18th power) electrons per second
,A shipping crate is a cube with volume 64 ft3. What is the internal height of the crate? -
(answer)4 ft
The cost of the bolts used to fasten the panels in an elevator cab is $5 for 4 bolts. If a particular
job calls for 80 bolts, what is the cost? - (answer)$100
Convert 4.12 x 10-5 kg to μg. - (answer)4.12 x 10 ^4μg
An 18 mm ball bearing weighs 23.79 grams. If we have a crate containing 500 of these ball
bearings, what is the weight in kilograms? - (answer)11.895 kg
Each outlet in an office building can handle 30 amps without being overloaded. If the office
building has 250 outlets, represent the total amps in terms of kA. - (answer)7.5 kA
The resistance in a copper wire measuring 160 meters is found to be 3.5 Ω. Express the
resistance per meter in terms of milli ohms. - (answer)21.875 milli ohms
The hole for each bolt on a panel is 12500 μm in diameter. Express this diameter in millimeters. -
(answer)12.5 mm
, Convert 1.34 x 10^13 μm to Mm. - (answer)13.4 Mm
For a series of tasks, the projected times for several projects are the following: 1 hour 45
minutes, 3 hours 20 minutes, 45 minutes, 2 hours 20 minutes, and 1 hour 40 minutes. What is the
total time for these projects? - (answer)9 hours 50 mins
A particular task is scheduled to take 4 hours 15 minutes. You and your team finish the job in
only 2 hours 34 minutes. How much time did the team have to spare? - (answer)1 hour 41
minutes
Solve for x: 2x + 4 = 11 - (answer)x = 7/2
Solve for t:
t/3 - 1/2 = 5/6 - (answer)t = 4
Solve for x:
0.24x + 0.42 = 1.74 - (answer)x = 5.50