Types of depencies
,Give this one a try later!
-Physical: One activity cannot start until on or the other is
partially/completely done "Hard logic"
-Safety: Simultaneous cause a safety hazard
-Resource: Two activities use the same resource
-Preferential: How a scheduler prefers work to be sequenced
Project Types:
Functional
Give this one a try later!
Divided by function entities with project carried out by functional/high
level managers
(Managed by functional managers)
Approx. ___% of work has no value added
Give this one a try later!
60
Project Types:
Project Matrix
Give this one a try later!
Managers oversee project and is responsible for completion of project and
is responsible for project completion.
, (Managed by project team managers)
Integration Clause
Give this one a try later!
Previous oral and written statements that are not referenced in the final
contract are not binding.
Sources of risk
Give this one a try later!
- Poor labor productivity
- Different site conditions
- Weather
- Design
NPV
Give this one a try later!
= F0 + F1/(1+r) + F2/(1+r)^2 = 0 (Example if t = 2)
Project Types:
Project Team
Give this one a try later!
Prev. years levy + new construction valuation
Types of depencies
,Give this one a try later!
-Physical: One activity cannot start until on or the other is
partially/completely done "Hard logic"
-Safety: Simultaneous cause a safety hazard
-Resource: Two activities use the same resource
-Preferential: How a scheduler prefers work to be sequenced
Project Types:
Functional
Give this one a try later!
Divided by function entities with project carried out by functional/high
level managers
(Managed by functional managers)
Approx. ___% of work has no value added
Give this one a try later!
60
Project Types:
Project Matrix
Give this one a try later!
Managers oversee project and is responsible for completion of project and
is responsible for project completion.
, (Managed by project team managers)
Integration Clause
Give this one a try later!
Previous oral and written statements that are not referenced in the final
contract are not binding.
Sources of risk
Give this one a try later!
- Poor labor productivity
- Different site conditions
- Weather
- Design
NPV
Give this one a try later!
= F0 + F1/(1+r) + F2/(1+r)^2 = 0 (Example if t = 2)