VERIFIED QUESTIONS AND ANSWERS||
GUARANTEED PASS|| LATEST VERSION 2026
Which inference test would you use to test if the variances of the two samples
are equal?
a. F test
b. 2 mean unequal variance t test
c. 2 mean equal variance t test
d. Paired t test - ANSWER-a. F test
When the same functions performed by different machines produce different
results, which type of variation can this be attributed to in a multi-vari chart?
a. Positional
b. Temporal
c. Cyclical
d. Ordinal - ANSWER-c. Cyclical
You have created a Supplier, Input, Process, Output, Customer (SIPOC)
diagram for your business system. You notice that the output of your process
has changed but there has been no change in the suppliers, inputs, or the
process. What information can be derived from this scenario?
a. The SIPOC diagram is not complete
,b. Changes in output are not controlled by the suppliers, inputs, or the process
c. The suppliers, inputs, or the process are unstable
d. Changes in output are not related to changes in suppliers, inputs, or the
process - ANSWER-a. The SIPOC diagram is not complete
In which measurement scale is the central location determined by the mode of
the data?
a. Nominal
b. Interval
c. Ordinal
d. Ratio - ANSWER-a. Nominal
The definition that states, 'total number of deficiencies divided by the total
number of units' represents the calculation for:
a. DPMO
b. RPN
c. DPU
d. DPO - ANSWER-c. DPU
Which of the following tools is used to identify, estimate, prioritize, and reduce
the risk of failure in CTQs through the development of actions (process
changes) and contingency plans based on Xs.
a. Process Flow Diagram.
b. Affinity Diagram.
c. Failure Modes and Effects Analysis (FMEA).
d. Histogram. - ANSWER-c. Failure Modes and Effects Analysis (FMEA).
,During project team meetings, the Team Leader is responsible for all of the
following activities EXCEPT:
a. Starts and ends the meeting on time
b. Stays on the agenda
c. Leads brainstorming sessions
d. Monitors how much time the team spends on each agenda item - ANSWER-
d. Monitors how much time the team spends on each agenda item
In which phase of DMAIC do you define the Roles and Responsibilities of the
Improvement Team?
a. Analyze
b. Define
c. Measure
d. Improve - ANSWER-b. Define
Multivoting is a variation of which of the following team tools?
a. Brainstorming
b. Force field analysis
c. Nominal group techniques
d. Consensus - ANSWER-c. Nominal group techniques
Excessive conflict within a work team:
I. Has a negative effect on team members and should be
avoided
, II. Has a positive effect on creating alternate solutions
III. Most often results in lose-lose situations
a. I only
b. I and III only
c. II and III only
d. III only - ANSWER-b. I and III only
A Balance Scorecard should include:
a. The Presidents Vision for the company
b. Financial and nonfinancial metrics
c. A calibrated measurement system
d. Electronic signage
e. The Quality Management System - ANSWER-b. Financial and nonfinancial
metrics
One of the components of the JIT process is/are:
a. 5 Whys
b. Poka-Yoke
c. In-Station QC
d. Pull System
e. All of the above - ANSWER-d. Pull System
One of the components of Autonomation is/are:
a. Poka-Yoke