QUESTIONS AND ANSWERS SURE A+
✔✔50) A competent signal person must be stationed at all times whenever a crane is -
✔✔Approaching the minimum safe distance from an energized power line
✔✔51) If two identical slings are used at an angle to the load , each sling - ✔✔Bears
more than h the weight of the load
✔✔52) A sudden loss of crane load may cause a - ✔✔whiplash effect
✔✔53) Symptoms associated with overheating include all of the following except -
✔✔Gray, tingling skin
✔✔54) When lifting loose materials such as pipe or bar stock, use a - ✔✔Double-wrap
choker hitch
✔✔55) When a mobile crane is being moved without direction from the rigger, three
travel signals from the crane's horn mean the - ✔✔Crane is traveling in reverse
✔✔56) When should tag lines be attached - ✔✔Before the load is lifted
✔✔57) crane or load comes in contact with power lines, the crane operator should -
✔✔Stay in the cab of the crane if possible
✔✔58) A load of pipe is most commonly lifted using - ✔✔A choker hitch
✔✔1) Because of its toughness, shackles for most overhead lifting are made from: -
✔✔Forged steel
✔✔2) Which of the following is an incorrect statement about the shackle? - ✔✔When
using a shackle with a hook, body hung on the hook.
✔✔3) The space between the sling or chain and the load can become a: - ✔✔Pinch
point
✔✔4) The maximum load weight that a sling is designed to carry is the: - ✔✔Rated
capacity
✔✔5) Which hand signal standards were developed for use with mobile and overhead
cranes? - ✔✔ASME
✔✔6) Most alloy steel chain slings can be used in temperatures up to: - ✔✔500°F