The Quality Assurance Plan: - - CORRECT ANSWER - >Is a government
management tool establishing staffing, training, pre-award activities, and surveillance
activities.
Testing is extremely important in construction quality management and is performed
by: - - CORRECT ANSWER
- >Both the contractor and the government
If the contractor does not provide an adequate superintendent, the contract allows
the contracting officer to: - - CORRECT ANSWER - >Require the contractor to assume
personal supervision of the work.
The Quality Control Plan: - - CORRECT ANSWER - >Is the foundation upon which
quality work is based and outlines planned quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality control tests
are: - - CORRECT ANSWER -
>Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable: - - CORRECT
ANSWER - >The contractor makes changes before acceptance.
1
, The contractor quality control organization: - - CORRECT ANSWER - >May vary in size
depending on the work being performed at a point in time.
The Quality Control Plan contains: - - CORRECT ANSWER - >Identification of individual
quality quality control personnel, including name, qualifications, assigned duties,
responsibilities and authorities.
The preconstruction conference and the coordination and mutual understanding
meeting (Navy) are: - - CORRECT ANSWER - >Conducted prior to the commencement
of any physical construction work.
A cumulative list of job deficiencies/rework items can be found in: - - CORRECT
ANSWER - >A deficiency tracking system/reworks items list.
What is a purpose of the coordination and mutual understanding and meeting
(Navy)? - - CORRECT
ANSWER - >To review the QC Plan with the contractor.
Which of the following is included in all three phases of the Three Phases of Control. -
- CORRECT ANSWER - >Safety.
Submittals are: - - CORRECT ANSWER - >Necessary to demonstrate that the proposed
materials, etc. are in compliance with the contract.
All submittals for government approval must be provided by the
2
NEW 2025
The Quality Assurance Plan: - - CORRECT ANSWER - >Is a government
management tool establishing staffing, training, pre-award activities, and surveillance
activities.
Testing is extremely important in construction quality management and is performed
by: - - CORRECT ANSWER
- >Both the contractor and the government
If the contractor does not provide an adequate superintendent, the contract allows
the contracting officer to: - - CORRECT ANSWER - >Require the contractor to assume
personal supervision of the work.
The Quality Control Plan: - - CORRECT ANSWER - >Is the foundation upon which
quality work is based and outlines planned quality control procedures.
Tests that are unannounced, randomly performed, and repeat quality control tests
are: - - CORRECT ANSWER -
>Quality Assurance tests
If initial review of the quality control plan shows it to be unacceptable: - - CORRECT
ANSWER - >The contractor makes changes before acceptance.
1
, The contractor quality control organization: - - CORRECT ANSWER - >May vary in size
depending on the work being performed at a point in time.
The Quality Control Plan contains: - - CORRECT ANSWER - >Identification of individual
quality quality control personnel, including name, qualifications, assigned duties,
responsibilities and authorities.
The preconstruction conference and the coordination and mutual understanding
meeting (Navy) are: - - CORRECT ANSWER - >Conducted prior to the commencement
of any physical construction work.
A cumulative list of job deficiencies/rework items can be found in: - - CORRECT
ANSWER - >A deficiency tracking system/reworks items list.
What is a purpose of the coordination and mutual understanding and meeting
(Navy)? - - CORRECT
ANSWER - >To review the QC Plan with the contractor.
Which of the following is included in all three phases of the Three Phases of Control. -
- CORRECT ANSWER - >Safety.
Submittals are: - - CORRECT ANSWER - >Necessary to demonstrate that the proposed
materials, etc. are in compliance with the contract.
All submittals for government approval must be provided by the
2