MODULE 1
a critical way that formal communication differs from informal is that that
formal communication is binding upon the parties and informal
communication in non binding true during communications with the
contractor the COR may provide clarification about concerns or issues
The COR may release information without consulting with the Contracting
Officer or Legal Counsel. false when dealing with noncompliance what is
the most preferred solution
Have the contractor repair or replace the defective or non-conforming
supplies, or reperform the non conforming services at no additional cost
If a contractor is delinquent on a portion of a contract, and that portion is
clearly severable from the continuing portion of the contract, the
Contracting Officer may terminate the deficient portion of the contract
using a Partial Termination.
True
MODULE 2
Which of the following is NOT an impact a Time and Materials contract
has on the COR's monitoring responsibilities?
,COR must ensure contractor is meeting requirements to receive profit
incentives s NOT an impact a Time and Materials contract has on the
COR's monitoring responsibilities.
What category of contract will they be awarding?
They will be awarding a services category of contract.
What type of contract should they use?
They should use a firm fixed price contract.
What fee type should they use?
They should use an incentive fee.
Which of the following is NOT a purpose of the evaluation criteria?
To reveal factors that will have no impact on the award decision is NOT a
purpose of the evaluation criteria.
What responsibility will a COR have during the source selection
evaluation? Perform
Performing a technical evaluation of offers received is a responsibility that
the COR will have during the source selection evaluation.
An authorized agency personnel needs to purchase several office supplies,
at a total estimated cost of $1,500. Which of the following Quick
Procurement Options would be best to use?
An authorized agency personnel needs to purchase several office supplies,
at a total estimated cost of $1,500. The Government-wide Commercial
Purchase Card would be the best quick procurement options to use.
Which of the following is true about fixed fee contracts?
A contractor's fee is a negotiated amount that is set at the inception of the
contract is true about fixed fee contracts.
What contracting method will Tisha and Juan employ?
Tisha and Juan will employ the competitive negotiations contracting
method.
,As an IPT member, the COR may __________________________ during
the Contract Award process. (Select all the apply.)
As an IPT member, the COR may assist KO with writing a Performance
Work Statement, provide technical advice prior to being assigned as a
COR, Perform a technical evaluation of proposals and assist in writing the
PWS as well as the evaluation factors for award during the Contract Award
process.
As COR Nominee, the COR may __________________________ during the
Contract Award process. (Select all that apply.)
As COR Nominee, the COR may assist KO with writing a Performance
Work Statement, provide technical advice prior to being assigned as a
COR, perform a technical evaluation of proposals, and assist in writing the
evaluation factors for award during the Contract Award process.
The Competition in Contracting Act (CICA), 10 U.S.C. 2304 and 41 U.S.C.
25 requires that KOs shall promote and provide for full and open
competition in soliciting offers and awarding government contracts.
However, contracting without providing full and open competition is
permitted by several exceptions stated in FAR 6.302. Which of the
following scenarios would NOT qualify as an exception to using full and
open competition?
The scenario: Caldwell Plumbing, Inc. is directly awarded a contract at the
request of the program officer who feels they are the best people for the job
due to their good reputation and previous experience, would NOT qualify
as an exception to using full and open competition.
To complete the award process, which of the following is NOT an action
taken by the KO?
Furnish executed contracts to all offerors, is NOT an action taken by the
KO.
An acquisition process addresses a supply or service gap between what
exists now and what is needed for an agency or service to fulfill its mission.
, True. An acquisition process addresses a supply or service gap between
what exists now and what is needed for an agency or service to fulfill its
mission.
To begin the acquisition process, the KO forms an Integrated Process Team
and takes into account influential factors that can impact the plan.
False. It is the planner, usually the program manager from the requiring
activity, who forms the IPT and begins the acquisition process.
Which of the following duties might a COR be tasked with in the
acquisition process? (Select all that apply.)
Perform market research, provide input for contract
administration/surveillance plans, and help with requesting funds are
duties that a COR might be tasked with in the acquisition process.
What is the principal purpose of acquisition planning?
The principal purpose of acquisition planning is to ensure that the
government meets its needs in the most effective, economical and timely
manner.
Effective market research assists the government in:
Effective market research assists the government in all of the above.
determining the correct scope of the requirement. understanding the
desired service or supply. understanding industry terminology.
A No-Year appropriated fund means the funds __________________.
A No-Year appropriated fund means the funds have no built-in time
limitation.
Information on the competitive climate, the intended use for the product or
service, and controls available to ensure successful performance give the
KO and the contractor a concise description of what the customer needs in
the requirements document.
True. Information on the competitive climate, the intended use for the
product or service, and controls available to ensure successful performance
give the KO and the contractor a concise description of what the customer
needs in the requirements document.