QUESTIONS ANSWERS COMPREHENSIVE
STUDY RESOURCE
●● Limited Scope Installation
Answer: Installation of only cables and termination/connectivity
hardware that utilizes pathways that are existing or will be installed by
others in a separate project
(TPMRM, page 1-3
●● What are some possible project assumptions a PM should not make
about a work site?
Answer: There may be environmental hazards (asbestos, chemically
contaminated areas, etc.)
TPMRM, page 1-3
●● What are some possible project assumptions a PM should not make
about retrofits and upgrades?
Answer: Existing premise ICT infrastructure may not be fully
documented and accounted for
, (TPMRM, page 1-3)
●● What are some possible project assumptions a PM should not make
about new constructions?
Answer: The basic building structure may be incomplete and may not
support ICT installation activities.
●● What are four examples of direct project costs?
Answer: 1. Costs associated with labor to perform the work
2. Cost of materials used
3. Cost of permits, licenses, and inspections
4. Cost of utilities, waste disposal, and other similar services to perform
work
●● What are the four types of indirect costs associated with a project?
Answer: 1. Customs Duty
2. Tariffs
3. Exchange Rates
4. Value-Added/Sales.Excise Tax
●● Who typically sets the exchange rate for a country?