According to the IBC, the "blank" is to hire the special inspector. -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔-owner or owners agent. 2009 IBC Section 1704.1
| | | | | | | |
According to the IBC, the "blank" is the responsible for the approval of a
| | | | | | | | | | | | | |
person's qualifications to act as a special inspector. - CORRECT
| | | | | | | | | |
ANSWER✔✔-code official. 2009 IBC, Section 1704.1 | | | | |
According to the IBC, discrepancy corrections are made known to the
| | | | | | | | | | |
building official by: - CORRECT ANSWER✔✔-final report. 2009 IBC,
| | | | | | | | |
Section1704.1.2
When is the code official to be made aware of a discrepancy found
| | | | | | | | | | | | |
during a special inspection? - CORRECT ANSWER✔✔-If it is not
| | | | | | | | | |
corrected by the contractor. 2009 IBC, Section 1704.1.2
| | | | | | |
According to the Model Program for Special Inspection, the special
| | | | | | | | | |
inspector is to document work that is nonconforming: - CORRECT
| | | | | | | | | |
ANSWER✔✔-In a written report - Section II B 4 - Model Programs
| | | | | | | | | | |
,According to the Model Program for Special Inspection, the special
| | | | | | | | | |
inspector is to prepare written report of inspection: - CORRECT
| | | | | | | | | |
ANSWER✔✔-After each inspection visit - Section II B 5 - Model | | | | | | | | | | |
Programs
According to the Model Program for Special Inspection, which of the
| | | | | | | | | | |
following items does not need to be included in each inspection report?
| | | | | | | | | | |
|- CORRECT ANSWER✔✔-Description of discussions with the contractor -
| | | | | | | |
|Section B 5 - Model Programs | | | | |
According to the Specification for Structural Joints using high strength
| | | | | | | | | |
bolts, the nominal diameter of standard bolt holes shall be how much
| | | | | | | | | | | |
larger than the nominal bolt diameter? - CORRECT ANSWER✔✔-1/16
| | | | | | | | |
inch - Specification for Structural Joints Table 3.1
| | | | | | |
Discrepancies in the work shall be brought to the immediate attention
| | | | | | | | | | |
of the "blank" for corrective action. - CORRECT ANSWER✔✔-the
| | | | | | | | |
contractor - 2009 IBC, Section 1704.1.2. | | | | |
The special inspector shall furnish inspection reports to the "blank" and
| | | | | | | | | | |
to the "blank"? - CORRECT ANSWER✔✔-Building Official and Registered
| | | | | | | | |
Design professional |
, The special inspector shall provide continuos inspection of: - CORRECT
| | | | | | | | | |
ANSWER✔✔-Single-pass fillet welds greater than 5/16 inch in size - | | | | | | | | | |
2099 IBC, Table 1704.3, Item 5.3
| | | | |
The special inspections required by this code are not required where the
| | | | | | | | | | |
|work is done on the premise of a? - CORRECT ANSWER✔✔-Approved
| | | | | | | | | | |
fabricator - 2009 IBC, Section 1704.2.2
| | | | |
The special inspection of the steel fabrication process shall not be
| | | | | | | | | | |
required where the fabricator does not perform any? - CORRECT
| | | | | | | | | |
ANSWER✔✔-heating operations - 2009 IBC, Section 1704.3, Exceptions | | | | | | | |
#1 |
According to the Specifications for Structural Steel Buildings, ASTM
| | | | | | | | |
Standard "blank" is to be used for the material test for steel sheets. -
| | | | | | | | | | | | | |
CORRECT ANSWER✔✔-A568 - Section A31, Specifications for Structural
| | | | | | | |
Steel Buildings |
According to the Specifications for Structural Steel Buildings, the "blank"
| | | | | | | | |
conducts the material tests for identification of the structural steel. -
| | | | | | | | | | | |
CORRECT ANSWER✔✔-Fabricator or Testing Laboratory - Section A31,
| | | | | | | |
Specifications for Structural Steel Buildings. | | | |
According to the Specifications for Structural Steel Buildings, which of
| | | | | | | | | |
the following steel members are allowed to be unidentified steel? -
| | | | | | | | | | |
Answers
According to the IBC, the "blank" is to hire the special inspector. -
| | | | | | | | | | | | |
CORRECT ANSWER✔✔-owner or owners agent. 2009 IBC Section 1704.1
| | | | | | | |
According to the IBC, the "blank" is the responsible for the approval of a
| | | | | | | | | | | | | |
person's qualifications to act as a special inspector. - CORRECT
| | | | | | | | | |
ANSWER✔✔-code official. 2009 IBC, Section 1704.1 | | | | |
According to the IBC, discrepancy corrections are made known to the
| | | | | | | | | | |
building official by: - CORRECT ANSWER✔✔-final report. 2009 IBC,
| | | | | | | | |
Section1704.1.2
When is the code official to be made aware of a discrepancy found
| | | | | | | | | | | | |
during a special inspection? - CORRECT ANSWER✔✔-If it is not
| | | | | | | | | |
corrected by the contractor. 2009 IBC, Section 1704.1.2
| | | | | | |
According to the Model Program for Special Inspection, the special
| | | | | | | | | |
inspector is to document work that is nonconforming: - CORRECT
| | | | | | | | | |
ANSWER✔✔-In a written report - Section II B 4 - Model Programs
| | | | | | | | | | |
,According to the Model Program for Special Inspection, the special
| | | | | | | | | |
inspector is to prepare written report of inspection: - CORRECT
| | | | | | | | | |
ANSWER✔✔-After each inspection visit - Section II B 5 - Model | | | | | | | | | | |
Programs
According to the Model Program for Special Inspection, which of the
| | | | | | | | | | |
following items does not need to be included in each inspection report?
| | | | | | | | | | |
|- CORRECT ANSWER✔✔-Description of discussions with the contractor -
| | | | | | | |
|Section B 5 - Model Programs | | | | |
According to the Specification for Structural Joints using high strength
| | | | | | | | | |
bolts, the nominal diameter of standard bolt holes shall be how much
| | | | | | | | | | | |
larger than the nominal bolt diameter? - CORRECT ANSWER✔✔-1/16
| | | | | | | | |
inch - Specification for Structural Joints Table 3.1
| | | | | | |
Discrepancies in the work shall be brought to the immediate attention
| | | | | | | | | | |
of the "blank" for corrective action. - CORRECT ANSWER✔✔-the
| | | | | | | | |
contractor - 2009 IBC, Section 1704.1.2. | | | | |
The special inspector shall furnish inspection reports to the "blank" and
| | | | | | | | | | |
to the "blank"? - CORRECT ANSWER✔✔-Building Official and Registered
| | | | | | | | |
Design professional |
, The special inspector shall provide continuos inspection of: - CORRECT
| | | | | | | | | |
ANSWER✔✔-Single-pass fillet welds greater than 5/16 inch in size - | | | | | | | | | |
2099 IBC, Table 1704.3, Item 5.3
| | | | |
The special inspections required by this code are not required where the
| | | | | | | | | | |
|work is done on the premise of a? - CORRECT ANSWER✔✔-Approved
| | | | | | | | | | |
fabricator - 2009 IBC, Section 1704.2.2
| | | | |
The special inspection of the steel fabrication process shall not be
| | | | | | | | | | |
required where the fabricator does not perform any? - CORRECT
| | | | | | | | | |
ANSWER✔✔-heating operations - 2009 IBC, Section 1704.3, Exceptions | | | | | | | |
#1 |
According to the Specifications for Structural Steel Buildings, ASTM
| | | | | | | | |
Standard "blank" is to be used for the material test for steel sheets. -
| | | | | | | | | | | | | |
CORRECT ANSWER✔✔-A568 - Section A31, Specifications for Structural
| | | | | | | |
Steel Buildings |
According to the Specifications for Structural Steel Buildings, the "blank"
| | | | | | | | |
conducts the material tests for identification of the structural steel. -
| | | | | | | | | | | |
CORRECT ANSWER✔✔-Fabricator or Testing Laboratory - Section A31,
| | | | | | | |
Specifications for Structural Steel Buildings. | | | |
According to the Specifications for Structural Steel Buildings, which of
| | | | | | | | | |
the following steel members are allowed to be unidentified steel? -
| | | | | | | | | | |