A. Roles and Permissions Matrix
B. Organizational modelling
C. Business capability analysis
D. Decision modelling - ANSWER D. Decision modelling
Explanation: BABoK V3.0 - Section 7.1.4.1 - Model Requirements - Paragraph 3 - Point #2 -
Rationale: models represent the 'why' of a change. Techniques used to represent the
rationale include Decision Modelling; Scope Modelling; Business Model Canvas; Root Cause
Analysis; and Business Rules Analysis
2. The main reason for implementing appropriate levels of abstraction is because:
A. Not all stakeholders find value in the entire set of requirements
B. Requirements do not have necessary attributes
C. Requirements have missing components
D. Stakeholders don't have interest - ANSWER A. Not all stakeholders find value in the
entire set of requirements
Explanation: BABoK V3.0 - Section 7.1.4.4 - Implement the Appropriate Levels of Abstraction
- The level of abstraction of a requirement varies based on the type of requirement and
audience for the requirement. Not all stakeholders require or find value in the complete set
of requirements and models. It may be appropriate to produce different viewpoints of
requirements to represent the same need for different stakeholders. Business analysts take
special care to maintain the meaning and intent of the requirements over all
representations.
1
, 3. Which of the following is used to record the meaning of relevant business terms while
analyzing requirements?
A. Glossary
B. Scope model
C. State model
D. Data dictionary - ANSWER A. Glossary
Explanation: BABoK V3.0 - Section 7.1.6 - Techniques - Glossary: used to record the meaning
of relevant business terms while analyzing requirements
4. Which of the following can be used for quality control when verifying requirements and
designs?
A. Data model
B. Templates
C. Information management approach
D. Checklists - ANSWER D. Checklists
Explanation: BABoK V3.0 - Section 7.2.4.3 - Checklists - Checklists are used for quality control
when verifying requirements and designs.
5. Which of the following stakeholders can participate in specify and model requirements
task?
A. Only Sponsor and PM
B. Only developers and implementation SME
C. Only technical architect and PM
D. Any stakeholders - ANSWER D. Any stakeholders
2