CPM Study guide Questions With Correct
Answers
Which interpersonal skill is displayed by developing a vision and
| | | | | | | | | |
strategy, and inspires people to achieve that vision and strategy? -
| | | | | | | | | | |
CORRECT ANSWER✔✔-Leadership |
Control procurements is performed as part of which process group?" -
| | | | | | | | | | |
CORRECT ANSWER✔✔-Monitoring and Controlling | | |
A manager and the head of engineering discuss a change to a major
| | | | | | | | | | | | |
work package. After the meeting, the manager contacts you and tells
| | | | | | | | | | |
you to complete the paperwork to make the change. This is an example
| | | | | | | | | | | | |
of - CORRECT ANSWER✔✔-A project expediter position.
| | | | | |
During a team meeting, a team member asks about the measurements
| | | | | | | | | | |
that will be used on the project to judge performance. The team
| | | | | | | | | | | |
member feels that some of the measures related to activities assigned
| | | | | | | | | | |
him are not valid measurements. The project is BEST considered in what
| | | | | | | | | | |
part of the project management process? - CORRECT ANSWER✔✔-
| | | | | | | | |
Executing
, Your company just won a major new project. It will begin in three
| | | | | | | | | | | | |
months and is valued at 2m USD. You are the project manager for an
| | | | | | | | | | | | | |
existing project. What is the FIRST thing you should do once you hear of
| | | | | | | | | | | | | |
the new project? - CORRECT ANSWER✔✔-Ask management how the
| | | | | | | | |
new project will affect your project
| | | | |
You are a new project manager who has never managed a project
| | | | | | | | | | | |
before. It would be BEST in this situation to rely on _____ during
| | | | | | | | | | | | |
planning in order to improve your chance of success. - CORRECT
| | | | | | | | | | |
ANSWER✔✔-Historical information |
During project executing, a team member comes to the project
| | | | | | | | | |
manager because he is not sure of what work he needs to accomplish
| | | | | | | | | | | | |
on the project. Which of the following documents contain detailed
| | | | | | | | | |
descriptions of work packages? - CORRECT ANSWER✔✔-WBS Dictionary| | | | | | |
During a meeting with some of the project stakeholders, the project
| | | | | | | | | | |
manager is asked to add work to the project scope. The project manager
| | | | | | | | | | | |
had access to correspondence about the project before the project
| | | | | | | | | | |
charter was signed and remembers that the project sponsor specifically
| | | | | | | | | |
denied funding for the scope mentioned by these stakeholders. The
| | | | | | | | | |
BEST thing for the project manager to do is to: - CORRECT ANSWER✔✔-
| | | | | | | | | | | |
Tell the stakeholders the scope cannot be added.
| | | | | | |
Your project management plan results in a project schedule that is too
| | | | | | | | | | | |
long If the project network diagram cannot change but you have extra
| | | | | | | | | | | |
Answers
Which interpersonal skill is displayed by developing a vision and
| | | | | | | | | |
strategy, and inspires people to achieve that vision and strategy? -
| | | | | | | | | | |
CORRECT ANSWER✔✔-Leadership |
Control procurements is performed as part of which process group?" -
| | | | | | | | | | |
CORRECT ANSWER✔✔-Monitoring and Controlling | | |
A manager and the head of engineering discuss a change to a major
| | | | | | | | | | | | |
work package. After the meeting, the manager contacts you and tells
| | | | | | | | | | |
you to complete the paperwork to make the change. This is an example
| | | | | | | | | | | | |
of - CORRECT ANSWER✔✔-A project expediter position.
| | | | | |
During a team meeting, a team member asks about the measurements
| | | | | | | | | | |
that will be used on the project to judge performance. The team
| | | | | | | | | | | |
member feels that some of the measures related to activities assigned
| | | | | | | | | | |
him are not valid measurements. The project is BEST considered in what
| | | | | | | | | | |
part of the project management process? - CORRECT ANSWER✔✔-
| | | | | | | | |
Executing
, Your company just won a major new project. It will begin in three
| | | | | | | | | | | | |
months and is valued at 2m USD. You are the project manager for an
| | | | | | | | | | | | | |
existing project. What is the FIRST thing you should do once you hear of
| | | | | | | | | | | | | |
the new project? - CORRECT ANSWER✔✔-Ask management how the
| | | | | | | | |
new project will affect your project
| | | | |
You are a new project manager who has never managed a project
| | | | | | | | | | | |
before. It would be BEST in this situation to rely on _____ during
| | | | | | | | | | | | |
planning in order to improve your chance of success. - CORRECT
| | | | | | | | | | |
ANSWER✔✔-Historical information |
During project executing, a team member comes to the project
| | | | | | | | | |
manager because he is not sure of what work he needs to accomplish
| | | | | | | | | | | | |
on the project. Which of the following documents contain detailed
| | | | | | | | | |
descriptions of work packages? - CORRECT ANSWER✔✔-WBS Dictionary| | | | | | |
During a meeting with some of the project stakeholders, the project
| | | | | | | | | | |
manager is asked to add work to the project scope. The project manager
| | | | | | | | | | | |
had access to correspondence about the project before the project
| | | | | | | | | | |
charter was signed and remembers that the project sponsor specifically
| | | | | | | | | |
denied funding for the scope mentioned by these stakeholders. The
| | | | | | | | | |
BEST thing for the project manager to do is to: - CORRECT ANSWER✔✔-
| | | | | | | | | | | |
Tell the stakeholders the scope cannot be added.
| | | | | | |
Your project management plan results in a project schedule that is too
| | | | | | | | | | | |
long If the project network diagram cannot change but you have extra
| | | | | | | | | | | |