Latest Update 2026
Question 1
pts
Your client has requested a change that is considered feasible but is outside of the already
approved project scope. What should occur if the change is approved?
A. The project sponsor should be consulted
B. The request should not be approved
Correct!
C. The relevant baseline will require changing
D. The person making the change request should be removed from the
project to avoid conflict of interest
C is correct. Making changes to a project that are not part of the project scope is acceptable if
the relevant process is followed and the relevant baseline is changed to reflect the additional
information. Remember that a baseline is the original baseline plus any approved changes.
A, B, and D are incorrect. A is incorrect because the project sponsor was either consulted or
informed about the change as part of the normal integrated change control process, which will
approve the change, so there is no special reason to inform them now. B is incorrect because if
the change request is feasible, it should be considered and not just declined. D is incorrect
because it is wrong to think that there is conflict of interest simply because someone raises a
change request.
, Question 2
pts
How do agile methods handle the issue that there is often a gap between the real business
requirements and the business requirements originally stated?
Correct!
A. Requirements
B. Scope
C. Epics
D. WBS
A is correct. The requirements constitute the product backlog in a project that is using the agile
approach to development.
B, C, and D are incorrect because in an agile project, requirements constitute the product
backlog in a project.
A. Every documented change request must be approved, deferred, or rejected
Correct!
B. All change requests should be considered by the change control board
C. They may be initiated verbally