ACCURATE ANSWERS -UPDATED
2026\27
The purpose of|COMPLETE
Construction Quality Management is to: -Accurate answer
Achieve the quality established by properly developed requirements through the
combined responsibility, but seperate efforts of contractpr smd government
personnel.
Construction Quality Management is the performance of tasks, which ensure that
construction is performed. -Accurate answer According to plans and
specifications, on time, within a defined budget and a safe work environment.
Partnering relationships are based upon: -Accurate answer Building trust and
dedication to common goals
It is the responsibility of Quality Assurance Personnel to: -Accurate answer
Periodically verify that the contractors system of control is working effectively.
An effective contractor quality control program will: -Accurate answer Be an
incentive for work to be done correctly the first time resulting in earlier
completion, reduced field overhead costs, and greater profits.
The success or failure of all contractors is based upon: -Accurate answer The
ability to control costs, finance work, estimate jobs, schedule the work, and
maintain effective quality control.
Quality Assurance Personnel have the responsibility to: -Accurate answer Require
contractors to maintain the quality specified in the plans and specifications.
, Inspection is: -Accurate answer The process by which ongoing and completed
work is examined
During the punch-out inspection of a project: -Accurate answer Quality Assurance
Personnel must assure that the contractor prepares a punch-list and makes
corrections.
If there is a disagreement whether the contractors work complies with the contract:
-Accurate answer The government makes the final determination
Characteristics that describe a definable feature of work include: -Accurate answer
Cross-referenced listings to the contractors construction schedule that may have
more than one definable feature under a section of the specifications.
The _____________________ consists of daily checks of the work to assure
continuing compliance with contract requirements. -Accurate answer Follow-up
phase
The Quality Assurance Plan: -Accurate answer Is a government management tool
establishing staffing, training, pre-award activities, and surveillance activities.
Testing is extremely important in construction quality management and is
performed by: -Accurate answer Both the contractor and the government
If the contractor does not provide an adequate superintendent, the contract allows
the contracting officer to: -Accurate answer Require the contractor to assume
personal supervision of the work.