What are liquidated damages ✔Correct Answer-an amount of money that is assessed to the
contractor for a failure to meet a specified contract completion date
what are the four options for dispute resolution ✔Correct Answer-full litigation, mediation,
mini trial, arbitration
what is a claim ✔Correct Answer-an issue that occurs during construction and remains
unresolved after the job is complete
what is the first step in a progress payment process ✔Correct Answer-complete a document
called a schedule of values
what member represents the work site's company leadership ✔Correct Answer-
superintendent
what are construction operations ✔Correct Answer-actual work that it takes to build the
project, such as laying the foundation or framing the walls
what is an issue that the on-site management is concerned about ✔Correct Answer-material
and equipment deliveries
what is infrastructure ✔Correct Answer-the basic physical and organizational structures and
facilities (roads, bridges, buildings) needed for the operation of community or society
what three things must a superintendent do before construction work can begin ✔Correct
Answer-set up filed office, organize job site, establish the work hours
all heavy equipment and job vehicles must have what ✔Correct Answer-backing-up alarm
signals
what is the drug and alcohol policy on a construction site ✔Correct Answer-zero tolerance
and possible consequences
what's a pro to using a Gnatt chart ✔Correct Answer-easy to read, illustrated scheduling, set
reasonable time frames
what are the three stages to building a precedence diagram schedule ✔Correct Answer-
planning, sequencing, and scheduling stages