◉ Which technique is most useful when stakeholders cannot clearly
articulate their needs
Answer: Prototyping
◉ Which artifact shows the relationship between requirements and
delivered components
Answer: Requirements traceability matrix
◉ Which artifact documents why the project was approved
Answer: Business case
◉ What best ensure is delivered features remain aligned to
objectives
Answer: Traceability
◉ Which technique best supports building shared understanding
among stakeholders
, Answer: Workshops
◉ Which individual is accountable for ensuring the project aligns
with business objectives
Answer: Project sponsor
◉ Which process group is responsible for establishing the project
vision and success criteria
Answer: Initiating
◉ Which process formally accepts completed deliverables
Answer: Validate scope
◉ Which metric compares the amount of work actually completed to
what was planned
Answer: Earned value
◉ Which organizational structure provides the least authority to the
project manager
Answer: Functional
◉ A team member completes a deliverable that does not meet
acceptance criteria which process should address this?