TESTED QUESTIONS AND CORRECT
ANSWERS
◉ Which of the following is a tangible or intangible measurable
output of one or more project activities?
Answer: deliverable
◉ You are managing a software development project and have
planned that the final deliverable will be brought into existence in
successively refined stages at prototype, pilot, testing and
deployment stages. In this case, you are viewing software
development as a(n)
Answer: adaptive approach
◉ The product owner for a clothing manufacturer/retailer has
tasked you with defining a development approach for a new line of
children's clothing. This organization has never sold clothing for
children, and no one on the team has had any experience with this
type of product. One very rigid consideration is that this particular
company wants a line of childrens clothing that is unique in the
market, so you cannot just import a line from another company and
rebrand it. Which development approach should you use in this
case?
,Answer: adaptive
◉ Scheduling constraints, the availability of funding, and the nature
of the involved stakeholders are all factors that are part of which
aspect of the model of considerations for selecting a development
approach?
Answer: project
◉ You are the project manager for information systems in a major
banking firm. This particular company has not had its own mobile
application. The senior VP for operations asked you, along with
others in the IT and operations groups, to define a project that will
produce an initial mobile application. The VP has been emphatic
about the fact that this application must meet all compliance
requirements for consumer use; other than that, your teams have
freedom in the design and operation of the app. These factors
suggest that you probably want to use which development
approach?
Answer: hybrid
◉ The project team size and location, the overall culture and
capability are all factors that are part of which aspect of the model of
considerations for selecting a development approach
Answer: organization
, ◉ Certain aspects of your retail store project allow you to plan for a
known outcome of the construction of your retail store location.
Other aspects of the market development and product testing are
less stable at the early stages because you want to establish a more
unique approach to your store. To bring about the final operating
store in your chosen location, which approach might you want to
adopt?
Answer: hybrid
◉ A(n) _____ is a collection of logically related project activities that
culminates in the completion of one or more deliverables
Answer: phase
◉ Degree of innovation, ease of change, requirements, and
regulations are all factors that are part of which aspect of the model
of considerations for selecting a development approach?
Answer: product, service, or result
◉ Although a(n) _____ is scheduled in a project plan, it has no
estimated duration and is used to provide information about
progress through the major segments.
Answer: milestone
◉ The most commonly used logical dependency between two
activities in a project plan is: