Vertical building projects are first designed by an
architect and then engineered by design engineers
while horizontal infrastructure projects are typically
designed and engineered by design engineers
True
False - Answer-True
Based on laws and regulations, privately financed
projects must utilize competitive bidding to procure a
construction firm.
Select one:
True
False - Answer-False
,2|Page
An agency construction manager firm is contracted
with the Owner, lead designer, and construction firm
on a project.
Select one:
True
False - Answer-false
A program manager is the same as a project
manager.
Select one:
True
False - Answer-false
Which of the following is not a method used to
procure a constructor?
Select one:
,3|Page
a. None of these
b. Best value
c. Job order contracting
d. Low bid
e. Qualifications-based selection - Answer-c. Job
order contracting
Which management activity listed below is where the
project manager is tasked with coordinating
subcontractors, planning sequences of construction,
and developing effective communication?
Select one:
a. None of these
b. Controlling
c. Organizing
d. Scoping
e. Planning - Answer-c. organizing
, 4|Page
This testing process helps to reduce the risk that
major project systems (HVAC, electrical, etc) will
work according to the project objectives, plans, and
specifications.
Select one:
a. Commissioning
b. As-builts
c. None of these
d. Notice to Proceed
e. Constructability review - Answer-a. commisioning
During the early stages of the engineering and
design phase of a project, the Owner typically
procures the lead design firm using qualifications-
based selection.
Select one:
True
False - Answer-true