Update Fast Reviewed from Current Exam
Blueprint | 150 Most Frequently Tested
Questions and Correct Answers with Detailed
Explanations | Complete Study Guide and
Mock Examination | Already Graded A+ |
Instant Download PDF
1. A construction company recognizes revenue over time primarily under
which accounting principle?
A. Matching principle
B. Revenue recognition principle
C. Cost principle
D. Full disclosure principle
✔ Correct Answer: B. Revenue recognition principle ✔
*Rationale: Revenue is recognized as performance obligations are satisfied over
time, not only at project completion.
2. Which document is most critical for establishing the original contract value
in construction accounting?
A. Change order log
B. Subcontractor invoice
C. Executed contract agreement
D. Daily job report
✔ Correct Answer: C. Executed contract agreement ✔
*Rationale: The signed contract defines the legally binding original contract value.
, 3. Work-in-progress (WIP) reporting is primarily used to:
A. Track employee attendance
B. Monitor project financial performance
C. Approve subcontractor hiring
D. Calculate tax depreciation
✔ Correct Answer: B. Monitor project financial performance ✔
*Rationale: WIP reports compare costs, billings, and progress to assess project
profitability.
4. What does “overbilling” indicate in construction accounting?
A. Costs exceed revenue
B. Revenue billed exceeds costs incurred
C. Project is unprofitable
D. Labor inefficiency exists
✔ Correct Answer: B. Revenue billed exceeds costs incurred ✔
*Rationale: Overbilling occurs when billing is ahead of actual progress or costs.
5. Which contract type places the greatest risk on the contractor?
A. Cost-plus contract
B. Time and materials contract
C. Fixed-price contract
D. Unit-price contract
✔ Correct Answer: C. Fixed-price contract ✔
*Rationale: The contractor bears cost overrun risk under a fixed price agreement.
6. Retainage in construction is best described as:
A. Early payment discount
B. Funds withheld until project completion
C. Subcontractor advance payment
D. Equipment depreciation reserve
✔ Correct Answer: B. Funds withheld until project completion ✔
*Rationale: Retainage ensures contractual completion and performance quality.
, 7. Which financial statement reflects a company’s financial position at a
specific point in time?
A. Income statement
B. Cash flow statement
C. Balance sheet
D. Job cost report
✔ Correct Answer: C. Balance sheet ✔
*Rationale: The balance sheet shows assets, liabilities, and equity at a point in
time.
8. Direct job costs typically include:
A. Office rent and utilities
B. Project manager salary
C. Materials and labor
D. Corporate insurance
✔ Correct Answer: C. Materials and labor ✔
*Rationale: Direct costs are directly attributable to a specific project.
9. A cost overrun occurs when:
A. Budget exceeds actual cost
B. Actual cost exceeds budget
C. Revenue exceeds costs
D. Profit margin increases
✔ Correct Answer: B. Actual cost exceeds budget ✔
*Rationale: Overruns occur when spending surpasses the estimated budget.
10.Which accounting method is most commonly used in long-term
construction contracts?
A. Cash basis
B. Accrual basis
C. Modified cash basis
D. Tax basis
, ✔ Correct Answer: B. Accrual basis ✔
*Rationale: Accrual accounting matches revenues and expenses over time.
11.Change orders primarily affect:
A. Payroll processing
B. Contract scope and cost
C. Equipment depreciation
D. Insurance premiums
✔ Correct Answer: B. Contract scope and cost ✔
*Rationale: Change orders modify the original contract terms and pricing.
12.A project is 60% complete. This percentage is typically used in:
A. Cash flow forecasting
B. Revenue recognition calculations
C. Equipment scheduling
D. Tax filing
✔ Correct Answer: B. Revenue recognition calculations ✔
*Rationale: Percentage of completion is used to recognize revenue over time.
13.What is the main purpose of a job cost report?
A. Track employee payroll taxes
B. Monitor project profitability
C. Approve vendor contracts
D. Record equipment purchases
✔ Correct Answer: B. Monitor project profitability ✔
*Rationale: It compares actual costs to budgeted costs per job.
14.Which of the following is an indirect cost?
A. Concrete materials
B. Site labor
C. Project supervisor salary
D. Steel beams