Jurisdictional codes and requirements - Answer✔ - should always be checked
when determining the location and other features of the EVSE.
Bollards, curbs, and wheel stops - Answer✔ - can protect charging equipment
from physical damage from vehicles.
Adequate site lighting - Answer✔ - increases the safety of an EVSE location.
Trailblazing signs - Answer✔ - are for directing drivers to the location of EV
charging equipment.
According to the ADA guidelines - Answer✔ - 4% of general parking spaces should
be accessible.
, ADA parking space guidelines - Answer✔ - can be used as a guide when
determining the number of EV charging spaces that should be made accessible.
ADA guidelines - Answer✔ - are useful when planning an EVSE installation
because all of the above.
Operable parts of accessible equipment - Answer✔ - should be located 15"-48"
above finish grade per ADA guidelines.
The maximum depth of a barrier - Answer✔ - such as a curb or housekeeping pad,
in front of accessible equipment is 10".
DC fast chargers - Answer✔ - pose accessibility challenges because their cables
and connectors are larger and heavier than standard Level 1 and Level 2 EVSE.
Benefits of commissioning the installation of electric vehicle supply equipment
(EVSE) - Answer✔ - include all of the above.
commissioning - Answer✔ - is the process that ensures mechanical, electrical, and
other building systems are installed, tested, and perform interactively in
accordance with design documents.
test EVSE ground fault response - Answer✔ - One of the tests performed by an
EVSE test set.