Critical Pat Analysis UPDATED ACTUAL and Correct Answers
Question: What does PERT stand for?
Answer:
Program Evaluation and Review Technique
Question: What does CPM stand for?
Answer:
Critical Path Method
Question: What is the primary purpose of PERT/CPM?
Answer:
To plan, schedule, and control projects consisting
of numerous tasks.
Question: Which organization developed PERT?
Answer:
The U.S. Navy
Question: What type of projects is CPM primarily used for?
Answer:
Industrial projects with known activity
times.
Question: What is a critical path?
Answer:
The longest path through a project network, consisting of critical activities.
Question: What is the first step in the PERT/CPM scheduling process?
Answer:
Develop a list of activities
that make up the project.
Question: What is an immediate predecessor in project scheduling?
Answer:
An activity that must be
completed before another activity can start.