Which of the following is a responsibility of the Integrated Product Team (IPT) during the Risk
management (RM) process? - Answers Develop and implement the risk process planning outlined in
key program documents and support the program manager (PM) and the Risk Management Board
(RMB) as required
During engineering and manufacturing development (EMD), risks should be identified related to
critical manufacturing process and key product characteristics in which of the following risk areas? -
Answers Manufacturing
Supply Chain
During the Materiel Solution Analysis (MSA) phase, proactive activities to prevent technical risks focus
on which of the following? - Answers Developing requirements
a moderate issue with staffing shortages on your program is being tracked. new developers were
estimated to be on staff by March 8, but it appears that this deadline will not be reached. What is an
appropriate action to monitor this issue? - Answers Update and review the issue regularly and
analyze potential changes to the issue level and potential associated risks.
What would be the appropriate corrective action for the following issue: a major water leak has
permanently damaged 45% of the servers used to control the cloud-based newtork infrastructure.
This has been desiganted a high issue. - Answers Control
Which stage of the issue management (IM) process is characterized by the following scenario: A test
of the new portable Doppler-based wind measuring system demonstrates that the system works well,
but the battery drains out after the system is left in stand-by mode for 5 hours. - Answers Issue
identification
The new high-tech deep-sea vessel that your program is developing requires five separate research
and development projects to create new materials and components. Each component relies on the
others to inform how it will be designed. Is this interdependency a risk or an opportunity? - Answers
Risk
Your program includes teams in six different locations. these teams need access to different pieces of
risk monitoring data in order to monitor, manage, and report risk. Which of the following risk
monitoring tools would be most appropriate? - Answers Risk management (RM) information system
You are managing a program for the U.S. Navy to devleop a new diving helmet with enhanced
visualization capabilities. This type of technology requires materials that have never been used in
high-pressure environments. Which of the following risk control approaches would be most
appropriate for this scenario? - Answers Design of experiments
What type of risks can be identified from a Monte Carlo Simulation? - Answers Cost and schedule risk
Which of the followinng are the most common sources of risk in acquistiion? - Answers cost,
schedule, and human systems integration
The following describes which type of category of risk: after testing a new prototype drone system,
the Program Executive Office (PEO) has determined that changes need to be made that will increase
the cost and push the schedule. If the schedule and cost estimates are not updated accordingly, the
program will not achieve its goals. - Answers Programmatic
What is a good method for using risk identification tools to identify risks? - Answers combine a top-
level method with a lower-level method.
Where are the liklihood and consequnce paramaters and thresholds documented? - Answers the
program risk process (PRP) document
Within a program, approval to move a program into the next acquistion phase is made at what level
of the organization structure? - Answers executive level
Which of the following is a good example of a framing assumption (FA)? - Answers contractors will
offer mature designs that allow prototypes to be delivered in five months
Which of the following is a critical success factor to ensure effective risk managemetn (RM)? -
Answers aligning government and contractor risk management
Which step of the Department of Defense (DoD) Risk Management Process consists of the actitives to
develop, implement, and document the risk magenment process? - Answers Planning
Compare and contrast the two primary techniques for Work Breakdown Structure (WBS) construction
- top-down and bottom-up - by selecting the most accurate statements below regarding the two
techniques. (select three that apply) - Answers The top-down method of WBS construction is
normally used in the procurements of products (i.e. hardware and / or software); The last three steps
, of the bottom-up method are to review and discuss the task categories to ensure they correctly
capture the tasks listed, to review and discuss the categories to ensure all tasks are listed under the
correct category, and to finalize the WBS; The bottom-up method is typically used with the acquisition
of services
Which component of the work breakdhow sturcture (WBS) is a natural management point for
planning that represents the work assigned to one responsible organizational element for a single
WBS element? - Answers Control account
Which of the following statements are true regarding the differences between a Program Work
Breakdown Structure (WBS) and a Contract WBS? (Select two that apply) - Answers A program WBS
includes both government and contractor efforts, whereas a contract WBS includes only contractor
efforts; A contract WBS groups the project's work elements that organize and define the total work
scope of the project, whereas a program WBS further details components of the system that are
needed for its completion.
A technical publication is what type of common element? - Answers Data
Which of the following defense materiel items or systems are used in a work breadown structure?
(Select three that apply) - Answers equipment
Data
Services
What are three process steps for constructing a network schedule using the PDM format? (Select
three that apply) - Answers Sequence the tasks
Determine resource requirements
Identify the task
Which 14-Point Schedule metric consists of incomplete tasks with missing predecessor and/or
successor tasks, and helps determine how well or poorly scheduled tasks are linked together? -
Answers Logic
Which of the folloing components of the Precedence Diagramming Method (PDM) is identified by
locating the automatically generated red bars? - Answers Critical Path
Which three categories do schedules primarily fall into? - Answers Gantt Chart
Network Diagrams
Milestone Charts
Which two of the folloiwng are characteristics of the use of Agile Project Management in scheduling?
- Answers Work closely with the customer in order to focus agile teams on the highest impact and
most current requirements; produce new or additional functionality that is fully usable in each series
of schedule sprints
Summary schedules graphically depict the contractually required events and milestones to accomplish
program objectives, whereas detailed schedules do what? - Answers Graphically depict the effort at
the work package and planning package level
According to your engineering notebook, the last several times you put together a Preliminary Design
Review (PDR) package, it took four days. You estimate that the effort for a new project will be twice as
difficult. You use this information to provide an estimate for eight days. Which type of estimating
technique is most appropriate in this situation? - Answers Analogy estimate
The end result of the Identification of Schedule Tasks step in the Schedule Development and
Management Process is identified in the course or in this comprehensive list of all the tasks to be
performed for the program. As a program manager (PM), what additional three pieces of information
can you include to this list? (select three that apply) - Answers Known predecessor or success
activities; total float for each task; required leads and lags
Given changes (budget cuts, schedule slips, etc) to a planned government solicitation, what is one
benefit of financial projections that is aided by a Cost-Volume-Profit analysis? - Answers A Cost-
Volume-Profit analysis helps to calculate whether changes will affect a company's ability to cover its
costs with its total sales revenue.
What do the Net Present Value tables provide for any combination of number of periods and discount
rates? - Answers The present value of those projected future cash payments
Which of the following are true about discount rate? - Answers The discount rate is often referred to
as the hurdle rate; The discount rate is highly subjective
What do profitability ratios indicate? - Answers How much net income is left to a company from its
sales
Which ratio indicates if a company carries excessive debt? - Answers Financial leverage ratio