Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Samenvatting

Summary Unit III Assignment.docx MBA 6951 Project Scope Document Managing Complex Projects MBA 6951 Introduction The project scope document is an important step in the project development process and is designed to bring the stakeholders and project man

Beoordeling
-
Verkocht
-
Pagina's
6
Geüpload op
30-07-2021
Geschreven in
2020/2021

Unit III A MBA 6951 Project Scope Document Managing Complex Projects MBA 6951 Introduction The project scope document is an important step in the project development process and is designed to bring the stakeholders and project manager together in order to set the overall boundaries of the project. This document covers the following topics; customer requirements, statement of work, deliverables, work breakdown structure and acceptance criteria. By thoroughly addressing each of these topics both Hi-Tek Manufacturing and the project manager will be on the same page concerning the project objectives, what is expected throughout the project, how the project will be completed and the criteria needed complete the project successfully. The overall objective of this project is to increase production rates by 35%; with the sub objectives of expanding floor space, new machine installation and shipping

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

MBA 6951


Project Scope Document


Managing Complex Projects


MBA 6951



Introduction

The project scope document is an important step in the project development process

and is designed to bring the stakeholders and project manager together in order to set the

overall boundaries of the project. This document covers the following topics; customer

requirements, statement of work, deliverables, work breakdown structure and acceptance

criteria. By thoroughly addressing each of these topics both Hi-Tek Manufacturing and the

project manager will be on the same page concerning the project objectives, what is

expected throughout the project, how the project will be completed and the criteria needed

complete the project successfully. The overall objective of this project is to increase

production rates by 35%; with the sub objectives of expanding floor space, new machine

installation and shipping and receiving expansion.

Customer Requirements

Hi-Tek Manufacturing is seeking to expand their current manufacturing facility to

increase production times and improve their shipping and receiving capabilities. In order to

house 30 additional CNC machines and the additional shipping a receiving space the

expansion needs to be 37,450 square feet of additional floor space. To effectively run the

new equipment requires extensive plumbing and electrical, this requires additional electric

panels and additional pumps to cycle the coolant from the holding tanks to the machinery.

Due to the weight of the new equipment the floor of the expansion needs to be twelve inches

, thick to support the weight. In addition to the machinery the expansion requires two

overhead cranes to enable operators to load and unload large parts from the machines. Hi-

Tek requires a specific machine layout to support the flow of work, this will be taken into

consideration during the expansion design phase.



Statement of Work

The expansion of Hi-Tek manufacturing’s production facility is to be completed in

four phases; development, design, construction and installation. Phase one of the project is

the development phase and it consists of purchasing the land needed to build the addition

production space as well as procuring the appropriate permits through the local government

office allowing the construction project to take place. This is a key milestone because if there

are issues procuring the land or permits runs the risk of not being able to expand their facility

at the current location.

Phase two of the project is the design phase. Here we identifying the specific

equipment that will go into the expansion and blueprint development. Identifying the

equipment is required to identify the exact specifications needed to design the new building

layout. The risk of not completing this during phase two is that inadequate building

materials may be used which can cause delays and additional resources to make the

corrections. Once the specifications are identified the engineers can begin the design of the

facility and develop the blueprints to start construction.

Phase three of the project is the physical construction new production area. The

addition adds 37,450 square feet of manufacturing space bringing the total square footage of

the facility to 125,000 square feet. The additional space and capabilities are projected to

increase Hi-Tek’s production capabilities by 35%. Phase four of the project is the installation

and calibration of the new equipment into the new area.

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
30 juli 2021
Aantal pagina's
6
Geschreven in
2020/2021
Type
SAMENVATTING

Onderwerpen

$7.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
helperatsof1 Wgu
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
2531
Lid sinds
5 jaar
Aantal volgers
2045
Documenten
7896
Laatst verkocht
4 dagen geleden
Best class tutorials

Well written guides to enhance your learning potential

4.0

441 beoordelingen

5
224
4
89
3
56
2
31
1
41

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen