Process Costing
Beginning Work in Process (BWIP) xx
Started in Process(SIP)/ Transferred-in/ Received from prior Dept xx
Finished and Transferred / Transferred-out (xx)
Ending Work in Process (EWIP) xx
EUP = Equivalent Units of Production
Format 1: In units
Total units actually completed xx
EUP - EWIP (Actual Quantity x % of Completion) xx
Total Equivalent Production using Average Method xx
EUP - BWIP (Actual Quantity x % of Completion) (xx)
Total Equivalent Production using FIFO Method xx
Format 2: Quantity Schedule
FIFO
Actual x Work Done (WD) = EUP
BWIP xx
SIP xx
Total xx
Transferred-out:
BWIP xx Incomplete Stage xx
SIP xx 100% xx
Finished and on hand xx 100% xx
EWIP xx Completed Stage xx
Total xx xx
Average
Actual x Work Done (WD) = EUP
BWIP xx
SIP xx
Total xx
Transferred-out xx 100% xx
Finished and on hand xx 100% xx
EWIP xx Completed Stage xx
Total xx xx
Beginning Work in Process (BWIP) xx
Started in Process(SIP)/ Transferred-in/ Received from prior Dept xx
Finished and Transferred / Transferred-out (xx)
Ending Work in Process (EWIP) xx
EUP = Equivalent Units of Production
Format 1: In units
Total units actually completed xx
EUP - EWIP (Actual Quantity x % of Completion) xx
Total Equivalent Production using Average Method xx
EUP - BWIP (Actual Quantity x % of Completion) (xx)
Total Equivalent Production using FIFO Method xx
Format 2: Quantity Schedule
FIFO
Actual x Work Done (WD) = EUP
BWIP xx
SIP xx
Total xx
Transferred-out:
BWIP xx Incomplete Stage xx
SIP xx 100% xx
Finished and on hand xx 100% xx
EWIP xx Completed Stage xx
Total xx xx
Average
Actual x Work Done (WD) = EUP
BWIP xx
SIP xx
Total xx
Transferred-out xx 100% xx
Finished and on hand xx 100% xx
EWIP xx Completed Stage xx
Total xx xx