Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Samenvatting

INF3705_notes Summary. Success.

Beoordeling
-
Verkocht
-
Pagina's
58
Geüpload op
20-11-2021
Geschreven in
2021/2022

INF305 Yellow = answered textbook questions Blue = unanswered questions Chapter 3 – Process Models Prescriptive process models prescribe a set of process elements:  Framework activities, tasks, work products, quality assurance… Generic framework activities:  Communication  Planning  Modeling  Construction Deployment Linear process model: 1. Waterfall model (Classic life cycle)  Systematic, linear, sequential approach  For projects with these characteristics: o The problem is well understood (well-defined requirements) o The delivery date is realistic o Major changes in requirements are unlikely  For when work flows in a reasonably linear fashion  The linear nature can lead to ‘blocking states’, where you have to wait for other team members to complete dependent tasks  Inappropriate model for today’s fast-paced changing software  Problems: o Real projects rarely follow a sequential flow o The customer has to state all requirements explicitly o Working version of the program appears late in the project  Software projects that would be amenable to the waterfall model: o A well-understood modification to an existing program o A straightforward implementation of a numerical calculation or business rule, even if it is complex o A constrained enhancement to an existing program Incremental process models: For when requirements are well-defined, and a limited set of software functionality must be provided quickly, and then refined later. 2. Incremental model  Combines elements of the waterfall model applied iteratively  Linear sequences each produce deliverable increments of software  The first increment is usually a core product, used by customers  Each increment focuses on the delivery of an operational product  Good when staffing is unavailable for a complete implementation  Increments can be planned to manage technical risks  Software projects amenable to the incremental model: o A project that has significant functionality that must be delivered in a very tight time frame (Add on extras later) 1 3. RAD model  An incremental model that emphasizes a short development cycle  A high-speed adaptation of the waterfall model, where rapid development is achieved by using component-based construction  For when requirements are understood and scope is constrained  For when business applications can be modularized  A fully functional system is constructed in a very short time  Each major function is addressed by a separate RAD team and then integrated to form a whole  To achieve rapid development, this model assumes the existence of: a project that can be modularized in a manner that allows major functionality to be delivered within 60-90 days (This isn’t always the case – sometimes timelines can be longer) Drawbacks:  For large projects, RAD requires sufficient human resources to develop the increments in parallel  Projects will fail if people don’t commit to rapid activities  If a system can’t be modularized, you can’t build components  Might not work if high performance is an issue  Might not be appropriate when technical risks are high Evolutionary process models: For when core requirements are well understood and a limited version of the product must be introduced, which will evolve over time. Iterative, and can easily accommodate product requirement changes. 4. Prototyping  For when the customer defines a set of general objectives  For when the developer is unsure of the form of the software  Can be used as a standalone process model, but is more commonly used as a technique that can be implemented within other models  The prototype helps to identify software requirements  It should be discarded (at least in part)  Problems with prototyping: o The customer sees a working version and wants to keep it o Developers may become comfortable with inefficient choices  Software projects amenable to the prototyping model: o Ones which involve human-machine interaction and/or heavy computer graphics o Ones where results can easily be examined without real-time interaction (e.g. command-driven systems using mathematical algorithms) i.e. not embedded software!  Process adaptations required if the prototype will evolve into a deliverable system / product: o More rigorous design rules and SQA procedures must be applied from the beginning 2 o The prototype must be designed with extensibility in mind and be implemented using a programming environment that is amenable to production system development o The prototype is initially a mechanism for identifying requirements, and then becomes the framework for extensions that will cause it to evolve into a production system 5. Spiral model  Combines the iterative nature of prototyping with the controlled and systematic aspects of the waterfall model  Rapid development of increasingly complete versions of software  Software is developed in a series of evolutionary releases  Each framework activity represents 1 segment of the spiral path  Risk-driven model: risk evaluation during each iteration  Anchor point milestones are noted for each evolutionary pass  This model can apply throughout the life of the software  Good for developing large-scale systems and software  Not good if you have a fixed budget, because project cost is revised as each circuit is completed  Prototyping reduces risks, and can be applied at any stage  Problems: o May be hard to convince customers that it’s controllable o Demands considerable risk assessment and expertise o Problems if a major risk is not uncovered and managed  What happens to the software as you move outwards along the spiral process flow: o The product moves towards a more complete state o The level of abstraction at which work is performed is reduced (i.e. implementation-specific work accelerates as we move further from the origin) 6. Concurrent development model  Represented as a series of framework activities, software engineering actions & tasks, and their associated states  All activities exist concurrently but reside in different states  What the states represent and how they come into play: o The different parts of a project (framework activities) will be at different stages of completeness (e.g. ‘under development’, ‘awaiting changes’, ‘done’), so you can say that all activities are being performed concurrently o The challenge is to manage the concurrency and to be able to assess the status of the project  A series of events are defined that will trigger transitions from state to state for each of the software activities / tasks  This model is applicable to all types of software development  Often used for the development of client/server applications  Provides an accurate picture of the current state of the project

Meer zien Lees minder
Instelling
University Of South Africa
Vak
INF3705 - Advanced Systems Development











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
University of South Africa
Vak
INF3705 - Advanced Systems Development

Documentinformatie

Geüpload op
20 november 2021
Aantal pagina's
58
Geschreven in
2021/2022
Type
SAMENVATTING

Onderwerpen

$3.79
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
ExellentStudyResources Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1098
Lid sinds
4 jaar
Aantal volgers
917
Documenten
2076
Laatst verkocht
3 weken geleden

3.6

149 beoordelingen

5
67
4
19
3
31
2
4
1
28

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen