Elliott, M.
1
Which of the following is the main reason a project closing can be time-consuming?
Resolving outstanding issues
Releasing the team early
Organizing needed documentation
Evaluating actuals to estimates
2
Which of the following reflects a team evaluation criterion?
Worked collectively to manage identified risks for the project
Met schedule requirements for completion of project tasks
Ensured completed deliverable was 95% defect-free
Managed conflicts between stakeholder groups interested in the project
3
Which of the following statements is true about the post-transfer follow-up process?
Following up takes place between the project manager and the project team.
Following up after the project should occur indefinitely.
Following up is done as a courtesy in order to demonstrate support.
Following up should be done in a face-to-face meeting.
4
Which of the following is the correct reason the team is released as the last step in the
closing process?
,
You may need team members to meet with the project sponsor to gain approval.
You may need them to sign off on deliverable.
You cannot release them until they have another project assignment.
You may need team members to help in the transfer of ownership.
5
Which of the following is an example of a lesson learned that is related to resources used
outside the organization?
The weekly delivery of project status reports facilitated the success of the project.
A piece of equipment on the production line broke down and caused a schedule delay.
A deliverable did not meet quality standards because it was not tested thoroughly.
One of the groups contracted for the project failed to meet production deadlines.
6
Which of following is true regarding warehousing information?
Most organizations use a paper storage system for warehousing project documents.
Most organizations have a specific file-naming convention for filing documentation.
Documents are warehoused at the end of each phase of a project.
Only the final project documents are warehoused for a project.
7
Which activity would Trina perform in Phase 3 of a project to create a plant nursery at a
local hardware store?
Manage changes to the deliverables.