Which of the following is the first step in creating a WBS? Identify all activities needed for the project Verify that the work has been properly sequenced Refer to the scope to identify the deliverable Identify all tasks needed to make the work manageable CONCEPT Creating a WBS 2 Which of the following is correct about gaining approval for a project plan? The schedule cannot be adjusted. The plan is accepted as is. Most projects require formal stakeholder approval. Before it can be approved, the plan must be established as the baseline for the project. CONCEPT Gaining Approval 3 Which of the following does NOT affect a time estimate? Equipment availability Effort estimates Schedule dependencies Communication requirements CONCEPT Time and Effort Estimates 4 Allen needs to know about actions related to a project he is associated with, however, he is not asked to provide advice and he has no decision-making authority. Which of the following RACI elements is assigned to Allen?Responsible Consulted Informed Accountable CONCEPT Responsibility Matrix 5 Which of the following individuals listed in the RACI performs the project work? Informed Accountable Consulted Responsible CONCEPT Responsibility Matrix 6 What of the following information is NOT included in the risk register for a project? Date risk recorded Classification of risk Description of risk Impact to project budget CONCEPT Classifying and Recording Risks 7 Which of the following is the longest string of dependent project activities required to complete a project in the shortest amount of time? Effort estimate Resource estimate Critical path Project schedule CONCEPT Project Schedule 8 Which of the following components of a project plan is completed first? Work breakdown structureProject budget Risk management plan Project schedule CONCEPT Project Planning 9 When developing the project budget, it is useful to refer to the project schedule. What information does the project schedule provide? Effort estimates for completing deliverables Documentation of costs related to similar deliverables A helpful reminder of planned project outcomes A list of identified requirements for deliverables CONCEPT Project Budgeting 10 In which of the following ways are activities different from tasks? Tasks are subordinate to activities. Tasks are used for sequencing the project work. Activities are minor pieces of project work. Activities provide specificity regarding the project work. CONCEPT Creating a WBS 11

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

PM375 Sophia Project Management Milestone 2
ALL ANSWERS 100% CORRECT Spring-2022 LATEST
SOLUTION GUARANTEED GRADE A+
1
Which of the following is the first step in creating a WBS?

Identify all activities needed for the project

Verify that the work has been properly sequenced

Refer to the scope to identify the deliverable

Identify all tasks needed to make the work manageable
CONCEPT
Creating a WBS
2
Which of the following is correct about gaining approval for a project plan?

The schedule cannot be adjusted.

The plan is accepted as is.

Most projects require formal stakeholder approval.

Before it can be approved, the plan must be established as the baseline for the project.
CONCEPT
Gaining Approval
3
Which of the following does NOT affect a time estimate?

Equipment availability

Effort estimates

Schedule dependencies

Communication requirements
CONCEPT
Time and Effort Estimates
4
Allen needs to know about actions related to a project he is associated with, however, he is not asked to
provide advice and he has no decision-making authority.

Which of the following RACI elements is assigned to Allen?

, Responsible

Consulted

Informed

Accountable
CONCEPT
Responsibility Matrix
5
Which of the following individuals listed in the RACI performs the project work?

Informed

Accountable

Consulted

Responsible
CONCEPT
Responsibility Matrix
6
What of the following information is NOT included in the risk register for a project?

Date risk recorded

Classification of risk

Description of risk

Impact to project budget
CONCEPT
Classifying and Recording Risks
7
Which of the following is the longest string of dependent project activities required to complete a
project in the shortest amount of time?

Effort estimate

Resource estimate

Critical path

Project schedule
CONCEPT
Project Schedule
8
Which of the following components of a project plan is completed first?

Work breakdown structure

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
19 januari 2022
Aantal pagina's
6
Geschreven in
2021/2022
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$13.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Allan100 Rasmussen College
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
648
Lid sinds
5 jaar
Aantal volgers
605
Documenten
3226
Laatst verkocht
6 dagen geleden

3.5

92 beoordelingen

5
36
4
17
3
15
2
5
1
19

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen