DAU 090 Exam 2
Question 1
4 out of 4 points
If Contract A is an indefinite delivery contract, what is the type of cost or pricing arrangement?
Selected Answer: d.
Not enough information to determine the cost or pricing arrangement
Answers: a.
Fixed-price
b.
Cost-reimbursement
c.
Time-and-materials
d.
Not enough information to determine the cost or pricing arrangement
Question 2
4 out of 4 points
Which statement is TRUE regarding interagency acquisitions?
Selected b.
Answer:
A Governmentwide acquisition contract (GWAC) is for information
technology.
Answers: a.
A Federal Supply Schedule (FSS) contract is a multi-agency contract (MAC).
b.
A Governmentwide acquisition contract (GWAC) is for information
technology.
,DAU 090 Exam 2
c.
A MAC is a type of GWAC.
d.
An indefinite delivery contract is a FSS contract.
Question 3
4 out of 4 points
Scenario: You have a requirement for site preparation that is valued at $138,539. You conduct
market research and find that there are four potential offerors for the solicitation that would
submit offers at fair market price.
Offeror Large Small 8(a) HUBZone SDVOSB EDWOSB WOSB
McHenry X X X
Elsesser X X
Murtaugh X X X
Currier X X X X
Question: Which one of the following procedures may you use in order to select an appropriate
source for this acquisition?
Selected Answer: b.
8(a) sole source
Answers: a.
Competitive 8(a)
b.
8(a) sole source
, DAU 090 Exam 2
c.
HUBZone set-aside
d.
HUBZone sole source
Question 4
4 out of 4 points
Which contracting method DOES NOT use price or cost as an evaluation factor for award?
Selected Answer: d.
Architect-Engineer selection procedures
Answers: a.
Simplified acquisition procedures
b.
Sealed bidding
c.
Contracting by negotiation
d.
Architect-Engineer selection procedures
Question 5
0 out of 4 points
For which one of the following acquisitions will the use of simplified acquisition procedures be
authorized?
Selected b.
Answer:
Acquisition of a commercial item using Federal Supply Schedules
Answers: a.
Question 1
4 out of 4 points
If Contract A is an indefinite delivery contract, what is the type of cost or pricing arrangement?
Selected Answer: d.
Not enough information to determine the cost or pricing arrangement
Answers: a.
Fixed-price
b.
Cost-reimbursement
c.
Time-and-materials
d.
Not enough information to determine the cost or pricing arrangement
Question 2
4 out of 4 points
Which statement is TRUE regarding interagency acquisitions?
Selected b.
Answer:
A Governmentwide acquisition contract (GWAC) is for information
technology.
Answers: a.
A Federal Supply Schedule (FSS) contract is a multi-agency contract (MAC).
b.
A Governmentwide acquisition contract (GWAC) is for information
technology.
,DAU 090 Exam 2
c.
A MAC is a type of GWAC.
d.
An indefinite delivery contract is a FSS contract.
Question 3
4 out of 4 points
Scenario: You have a requirement for site preparation that is valued at $138,539. You conduct
market research and find that there are four potential offerors for the solicitation that would
submit offers at fair market price.
Offeror Large Small 8(a) HUBZone SDVOSB EDWOSB WOSB
McHenry X X X
Elsesser X X
Murtaugh X X X
Currier X X X X
Question: Which one of the following procedures may you use in order to select an appropriate
source for this acquisition?
Selected Answer: b.
8(a) sole source
Answers: a.
Competitive 8(a)
b.
8(a) sole source
, DAU 090 Exam 2
c.
HUBZone set-aside
d.
HUBZone sole source
Question 4
4 out of 4 points
Which contracting method DOES NOT use price or cost as an evaluation factor for award?
Selected Answer: d.
Architect-Engineer selection procedures
Answers: a.
Simplified acquisition procedures
b.
Sealed bidding
c.
Contracting by negotiation
d.
Architect-Engineer selection procedures
Question 5
0 out of 4 points
For which one of the following acquisitions will the use of simplified acquisition procedures be
authorized?
Selected b.
Answer:
Acquisition of a commercial item using Federal Supply Schedules
Answers: a.