Improved currency exchange
Reduced cost
Foreign dependency
Increased administrative requirements
2) An 8a small disadvantaged business graduates from the 8a program after ____ years.
7
5
9
11
3) The Acquisition Strategy should normally be generated using an integrated product team
(IPT) approach, including representation from all of the players listed below EXCEPT the
_________.
Funds Manager
End User
Milestone Decision Authority
Contracting Officer
4) Which of the following are "best practices" that may be appropriate for software intensive
programs (Select all that apply)?
Consider the risks of reusing existing software
Generate new code whenever possible
To speed development, only test software at completion
Use metrics to manage and monitor risk
5) The __________ phase translates planning decisions, OSD programming guidance, and
Congressional guidance into detailed allocations of time-phased resource requirements.
Execution
Programming
, Planning
Budgeting
6) The final approval authority for system-related National Environmental Policy Act (NEPA)
documentation is the:
Component Acquisition Executive (CAE)
Program Manager (PM)
Environmental coordinator
Under Secretary of Defense (Environmental Security)
7) Monitoring the performance of risk-handling actions is involved in which step of the risk
management model?
Risk tracking
Risk analysis
Risk identification
Risk mitigation planning
8) If the Government has funded the entire development of an item, the Government is entitled
to _______ rights.
Limited
Restricted
Unlimited
Government purpose
9) A _______ is an aggregation of program elements that reflects a macro-level force mission
or support mission of DoD.
Budget
Major Force Program (MFP)
Program Objectives Memorandum (POM)
Future Years Defense Program (FYDP)
10) A "not invented here" mentality is considered: