Question 1 of 65
Which two statements are correct in regards to creating a
successful network design for a customer? (Choose two.)
Customer Design Requirements
You should understand the state of the customer's current network.
You should analyze current and future network behavior.
You should only consider greenfield network designs.
You should only consider brownfield network designs.
Correct
Question 2 of 65
What are the three phases of the Juniper lifecycle service
approach? (Choose three.)
Customer Design Requirements
Operate
Migrate
Plan
Build
Correct
Question 3 of 65
What are the two main sub-phases of the plan methodology?
(Choose two.)
Customer Design Requirements
Access
Scope
Design
Build
Correct
Question 4 of 65
Which two items are key RFP elements? (Choose two.)
Customer Design Requirements
Logical design requirements
Business requirements
Environmental requirements
Physical design requirements
Incorrect
, Correct :
Business requirements
Environmental requirements
Feedback : The business and environmental requirements are key RFP elements.
Question 5 of 65
The business continuity RFP element contains which two
requirements? (Choose two.)
Customer Design Requirements
Wired connection requirements
Traffic requirements
Network efficiency requirements
QoS requirements
Correct
Question 6 of 65
The environmental requirements RFP element contains which
two items? (Choose two.)
Customer Design Requirements
A summary the type of business the customer is in.
An explanation of why a new design is required.
A detailed report that describes the facility specifications.
The number of users and workstation requirements.
Incorrect
Correct :
A detailed report that describes the facility specifications.
The number of users and workstation requirements.
Feedback : The environmental requirements RFP element includes a detailed report that
describes the facility specifications and the number of users and workstation
requirements.
Question 7 of 65
The connectivity and throughput requirements RFP element
contains which two items? (Choose two.)
Customer Design Requirements
Hierarchical design considerations
Number of wireless connections needed
Traffic analysis
Functionality of each module within the design
Incorrect
Correct :
Number of wireless connections needed
, Traffic analysis
Feedback : The modular requirements RFP element includes the number of wireless
connections that are needed and a in-depth traffic analysis.
Question 8 of 65
What are two aspects of greenfield projects? (Choose two.)
Customer Design Requirements
New networks with few or no restraints to consider.
Old equipment that should be replaced.
Legacy applications that are no longer used.
Next-generation networks created from the ground up.
Correct
Question 9 of 65
When analyzing customer requirements, what are two of the
categories that customer requirements can be organized into?
(Choose two.)
Customer Design Requirements
Core
Access
Security
Availability
Correct
Question 10 of 65
When analyzing customer requirements, what are three of the
categories that customer requirements can be organized into?
(Choose three.)
Customer Design Requirements
Edge
Performance
Scalability
Manageability
Correct
Question 11 of 65
Which two statements are true in regards to design proposals?
(Choose two.)
You should add as much complexity as possible to your design proposal..
You should keep your design proposal as simple as possible.
, You should create the physical design before the logical design.
You should create the logical design before the physical design.
Correct
Question 12 of 65
Which two statements are true in regards to design proposals?
(Choose two.)
Customer Design Requirements
Security only needs to be considered after the network is in place and functioning.
Security should be considered throughout the design process.
You design proposal should be clearly documented.
There is no need to document your design proposal.
Correct
Question 13 of 65
Which two statements are correct in regards to modularity in
your network design? (Choose two.)
Customer Design Requirements
Modularity facilitates future growth and troubleshooting efforts.
Modularity provides hierarchical structure to your design.
Modularity provides a flat structure to your design.
Modularity can stop future growth and troubleshooting efforts.
Correct
Question 14 of 65
Which two statements describe business continuity? (Choose
two.)
Customer Organizational Structure
The prevention of interruption to mission-critical services.
The ability to reestablish full functionality quickly after a disaster.
Manually turning on a backup server after a disaster.
Manually loading previously backed up data.
Correct
Question 15 of 65
What are the last two steps of business continuity planning?
(Choose two.)
Customer Organizational Structure
know your network
test the plan