Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Case uitwerking

AtlasCom Case- Case Project Management Case Studies in Project, Program, and Organizational Project Management, ISBN: 9781118174296

Beoordeling
-
Verkocht
-
Pagina's
5
Cijfer
A
Geüpload op
13-02-2022
Geschreven in
2017/2018

This note includes my personal answer to cases in the book mentioned below: Milosevic, D. Z., Patanakul, P., & Srivannaboon, S. (2010). Case Studies in Project, Program, and Organizational Project Management. John Wiley and Sons Inc.

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

CASE STUDIES IN PROJECT MANAGEMENT SYSTEMS 1



AtlasCom
Dragan Z. Milosevic, Peerasit Patanakul, and Sabin Srivannaboon

I. PROBLEM & SOLUTION

Problem: The management perceived that the manufacturing productivity and quality of the
company have been declining. They attempted to use CPM to resolve the problem however it was
not effective due to its complexity. Now, what would be the best project management tool that the
team can use that would allow them to enhance the productivity and quality of their products?
Solution: It can be enhanced through the use of Six Sigma since it concentrates on increasing
efficiency, raising productivity, and delivering consistent products to consumers. Meanwhile, in
this methodology skilled and experienced workers are necessary due to the difficulty in applying
for Six Sigma accreditation.
II. EXECUTIVE SUMMARY

AtlasCom is a company that is widely known for manufacturing advanced and specialized
construction equipment and is operating for more than 50 years. However, it turned out that
AtlasCom was being left behind by its competitors due to its declining manufacturing productivity
and quality. Thus they did reengineering that involves two-tier teams to complete the project. The
team opted to use CPM schedule which was a network diagram technique for analyzing, planning,
and scheduling projects that demonstrates the project activities through nodes or arrows,
identifying which has the significant impact on project completion time and scheduling them to
meet the set date of completion with a reasonable and least cost. Also, the longest path in time
from start to finish is the critical path that shows the least time required to get the job done and has
the highest priority path to be managed. However, the second-tier team members found the CPM
schedule to be a bit complex, thus, they were unable to use it. As a result, they opted to use a short
- term outlook schedule wherein they would pull out activities from CPM that were owned by a
team member and were to be done in the coming two weeks, presenting them in a Gantt chart
format. However, a short-term outlook schedule is questionable in terms of accuracy in
information and it can get out of control if not under supervision since different members will
create their schedule. Thus, to solve the problem that could be beneficial up to the long run, the
usage of Six Sigma since it concentrates on increasing efficiency, raising productivity, and
delivering consistent products to consumers. Meanwhile, in this methodology skilled and
experienced workers are necessary due to the difficulty in applying for Six Sigma accreditation.

III. BRIEF HISTORY

AtlasCom is a company that is widely known for manufacturing advanced and specialized
construction equipment and is operating for more than 50 years. However, it turned out that
AtlasCom was being left behind by its competitors due to its declining manufacturing productivity
and quality. To address this problem, the company has decided to launch several projects that
include reengineering the factory layout. A two-tier team was appointed to complete the project.
The first tier was a cross-functional group that comprises middle managers responsible for
handling the project effort. This group was also the main project team. Whereas, the second tier is
an extended team of manufacturing specialists that is responsible for doing the project work.
Meanwhile, the main team has been provided basic project management training to fill in their

, CASE STUDIES IN PROJECT MANAGEMENT SYSTEMS 2


lack of a formal project management process and experience before hiring a consultant to help
develop a detailed CPM schedule.

In preparation for the execution of the project, the main team explained the CPM schedule
to the second-tier team and requested them to start with the work and to report the development in
a week. However, the second-tier team members found the CPM schedule to be a bit complex,
thus, they were unable to use it as a basis for planning, organizing, and reporting. As a result, a
quality improvement project including members from both teams was asked to find a solution to
the problem. After a week, they opted to use a short-term outlook schedule wherein they would
pull out activities from CPM that were owned by a team member and were to be done in the coming
two weeks, presenting them in a Gantt chart format.

IV. INDUSTRY ANALYSIS




V. COMPANY ANALYSIS

Gekoppeld boek

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
13 februari 2022
Aantal pagina's
5
Geschreven in
2017/2018
Type
Case uitwerking
Docent(en)
Dr. manahan
Cijfer
A

Onderwerpen

$5.98
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
GelC
1.0
(1)

Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
GelC Course Hero
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
5
Lid sinds
4 jaar
Aantal volgers
4
Documenten
34
Laatst verkocht
2 jaar geleden

1.0

1 beoordelingen

5
0
4
0
3
0
2
0
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen