Q&A
1
Which of the following is a common reason for an area to be red in a
dashboard?
•
Effort estimation
•
Approved changes
•
Risk identification
•
Budget concerns
CONCEPT
Project Communications
2
Which of the following is true regarding project methodologies?
•
The iterative methodology works better with an easily defined project.
•
The phase-based project methodology goes through phases sequentially.
•
The phase-based methodology allows for frequent adaptations.
•
The iterative methodology involves a more traditional approach.
CONCEPT
Project Methodologies
3
Which of the following is the primary focus of scope monitoring?
,SOPHIA PROJECT MANAGEMENT FINAL MILESTONE
Q&A
•
Cost
•
Quality
•
, SOPHIA PROJECT MANAGEMENT FINAL MILESTONE
Q&A
Time
•
Effort
CONCEPT
Monitoring Scope
4
Which of the following documents is used to monitor and track risks
to a project?
•
Network diagram
•
Status report
•
Risk register
•
Dashboard
CONCEPT
Managing Project Risks
5
When monitoring the project schedule, which task is performed by
the project team member?
•
Approves change requests to hire more labor to complete tasks
•
Records effort spent on tasks during the project
•
Compares actual time to complete a task to original time estimates
•
Considers resource realignment if tasks are off-track
CONCEPT
Monitoring Time