QUESTION 1
Which of the following components of a project plan details the items needed
to complete the project deliverables?
A. Project schedule
B. Resource plan
C. Project budget
D. Communication plan
QUESTION 2
Because Riley and her project team were skilled at marketing but not
photography, Riley contracted a photographer to take pictures of menu items
for a marketing campaign she and her team were doing for a local restaurant. If
the photographer was already booked for the dates Riley requested, causing
Riley to push back the pictures two weeks, which two items below were NOT
impacted in the project plan?
,PROJECT_MANAGEMENT_COMPETENCY_2_PRACTICE_MILESTONE Q & A
A. Project schedule
B. Project budget
C. Resource plan
D. Risk management plan
E. Communication plan
QUESTION 3
Which of the following is NOT a resource used to help identify project work?
A. Subject matter experts
B. Project team members
C. Project stakeholders
D. Similar project schedules
, QUESTION 4
Match each WBS process step below to its corresponding description.
1. Identify Deliverables A. Represents a major piece of
work needed to accomplish a
project.
2. Identify Activities B. Used to make project work more
manageable to schedule and track.
C. Based on information
defined in the scope
document.
QUESTION 5
Which of the following provides the expertise needed to accomplish each
component of a project?
A. Material
B. Supplier
C. Equipment
D. Technology
QUESTION 6