To ensure the program can progress in the current acquisition phase or transition to the next
acquisition phase program, specific accomplishments must be satisfactorily demonstrated
before a program. How does the Milestone Decision Authority communicate these exit criteria?
a) Product Support Package
b) Acquisition Strategy
c) Acquisition Decision Memorandum
d) Acquisition Program Baseline
Established at the Critical Design Review (CDR) during the Engineering and Manufacturing
Development (EMD) phase, this key input is used as the decision point that the system design is
ready to begin developmental prototype hardware fabrication or software coding with
acceptable risk.
a) Architecture Design
b) Systems Engineering Plan
c) Initial Product Baseline
d) Acquisition Decision Memorandum
Which of the following are featured in an Operational Test Readiness Review (OTRR)? (Select all
that apply.) - *WRONG*
a) -*An analysis of identified technical risks*
b) -*A review of system certifications*
c) -*A review of the Developmental Test and Evaluation exit criteria specified in the Test
and Evaluation Master Plan*
d) -A review of system specifications
The objective of this technical review is to resolve any discrepancies between the production-
representative item that has successfully passed Operational Test & Evaluation (OT&E) and the
associated documentation currently under configuration control.
a) Operational Test Readiness Review (OTRR)
b) Physical Configuration Audit (PCA)
c) Functional Configuration Audit (FCA)
d) System Functional Review (SFR)