without having sufficient funds to cover that expense has violated the
. [Select the appropriate public law (i.e., Misappropriation Act, Anti-Deficiency
Act, Bona Fide Need) that applies to the use of appropriated funds under specific circumstances.]
Anti-Deficiency
Act
Misappropriation
Act
Bona Fide Need
Rule
Reprogramming
Thresholds
2) The Army can transfer excess funds from a Procurement appropriation to
a Research, Development, Test, and Evaluation (RDT&E) appropriation to
cover a funding shortfall of $3 million without prior approval of Congress.
[Given a funding shortfall, apply the rules governing reprogramming of appropriated funds in each
appropriation category to resolve the problem.]
True
Fals
e
3) Select the best statement about the use of Technical Reviews in
the current acquisition environment. [Relate the different types of program
unique
specifications to their appropriate configuration baselines and technical review requirements.]
Technical Reviews should be tailored to assess development maturity
and risk and to determine readiness to proceed to the next phase.
Technical Reviews waste valuable Government and contractor time and
should be eliminated to allow more focus on program execution.
The same standard set of Technical Reviews should always be conducted
on every program to ensure the PM has complete data to support decisions.
Technical Reviews are essential since they are vehicles for program
problem solving and training new people on the details of the program.
,