Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

Project Management Processes in Organizations.

Rating
-
Sold
-
Pages
12
Grade
A+
Uploaded on
16-04-2022
Written in
2021/2022

Project Management Processes in Organizations.

Institution
Course

Content preview

Project Management Processes in Organizations
(PM600-1804B-01)
Scheduling Techniques for
Planning and Executing
Introduction
This lesson examines essential scheduling tools and techniques for planning
and executing the work of a project. This lesson explains the four
predecessor–successor relationships, along with lead time and lag time, used
to model the sequence of activities. Network diagrams are used to
graphically represent the sequence of activities. The critical path method is
applied to the network diagram after durations have been estimated to
discover the critical path in the sequence of activities. The critical chain
method is applied to the critical path network diagram to introduce schedule
buffers to account for uncertainties. The schedule compression techniques of
fast-tracking and crashing the schedule are used for optimizing the schedule
during planning and for keeping the work on schedule during execution.

Learning Materials
Predecessor–Successor Relationships

Every activity in a project schedule must have an activity that proceeds it,
except for the first activity, the start of the project, and every activity in a
project schedule must have a successor activity that follows it, except for the
last activity at the end of the project. Predecessor–successor
relationships are used to model the following four types of dependencies:

 Mandatory dependencies are naturally inherent in the work.
For example, before framing a house, the subfloor must be
constructed; thus, the predecessor activity is construct the
subfloor, and the successor is framing.
 Discretionary dependenciesrefer to preferred sequences of (Lewis,
activities that have alternative sequences. The preferences 2017)
may be because of accepted best practices of an
application area.

,  External dependencies refer to activities or events that are not a part
of the project that affect activities that are part of the project. For
example, needing Environmental Protection Agency approval before
building a section of railroad track could occur.
 Internal dependencies refer to the predecessor relationships of
activities within the project.

To fully understand how predecessor relationships work, project managers
must extend their definition of predecessor in the context of scheduling to
mean the driving activity, as demonstrated below. The predecessor–
successor relationships of the four types of dependencies are modeled by
using the following four logical relationships in conjunction with any lead
times or lag times:

 Finish-to-Start (FS): “A successor activity cannot start until a
predecessor activity has finished” (Project Management Institute,
2013), as depicted in the first diagram of Figure 1, where Task A is the
predecessor and Task B is the successor. However, in the second
diagram when the lead time is applied, the definition does not hold.
The lead time is indicated by the double red arrow in the second
diagram and represents the amount of lead the start of the successor
has before the finish of the predecessor. Thus, one’s meaning of the
word “predecessor” must be extended to mean the driving activity
because if the finish of Task A is delayed, it drives a late start for Task
B. Likewise, an early Task A finish drives an early Task B start, as shown
in diagrams 3 and 4, respectively, in Figure 1.



Lag time, the interval of time after Task A finishes that Task B would start,
works similarly. This principle of the “driving activity” will now be applied to
the remaining three predecessor relationships.

 Finish-to-Finish (FF): “A successor activity cannot finish until a
predecessor activity has finished” (Project Management Institute,
2013). Here again, when lead time is applied to the finish of the
successor, the definition does not hold because clearly the successor
activity can finish before the predecessor activity finishes. More
accurately stated, in the FF relationship, the finish of the predecessor
drives the finish of the successor. See Figure 2



 Start-to-Start (SS): “A successor activity cannot start until a
predecessor activity has started” (Project Management Institute,
2013). Here again, when lead time is applied to the start of the

Written for

Course

Document information

Uploaded on
April 16, 2022
Number of pages
12
Written in
2021/2022
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$8.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Nechemia17 Campbell University
Follow You need to be logged in order to follow users or courses
Sold
140
Member since
5 year
Number of followers
124
Documents
1880
Last sold
2 months ago
BEST HOMEWORK HELP AND TUTORING ,ALL KIND OF QUIZ or EXAM WITH GUARANTEE OF A

WELCOME TO MY WORLD, GET ALL KIND OF EXAMS ON THIS PAGE, COMPLETE TEST BANKS, SUMMARIES,STUDY GUIDES, PROJECT PAPERS, ASSIGNMENTS, CASE STUDIES AND YOU CAN ALSO COMMUNICATE WITH THE SELLER FOR ANY PRE WORK EXAMS, I ASSURE YOU A SATISFACTORY WORK IF YOU WILL USE MY WORK.

3.9

20 reviews

5
11
4
1
3
5
2
1
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions