EXAM QUESTIONS AND ANSWERS
A project manager's team has been efficiently delivering expected results in an environment
where budget and scope are fixed. Now, there is an increased demand for new skills due to
changes in the market.
- CORRECT ANSWER Meet the new demand by upgrading the existing team members' skills.
You are meeting with your team during a daily standup meeting. During the meeting Joe, a
team member, notifies the group that they have an impediment due to an issue with the testing
procedure. The procedure is not designed to test in the way the team member needs. Another
team member, Jenny begins telling the first team member how they have overcome this in the
past. How should you respond?
- CORRECT ANSWER Stop Jenny's explanation and ask her to meet up with Joe after the
meeting to go through the workaround steps
A contractor has sent an email request for urgent payment of their last installment on a project
that is going through a long execution stage with multiple contractors. How should the project
manager respond to this contractor's request?
- CORRECT ANSWER Act according to the agreed upon commitments in the procurement
management plan.
A project has the following need: 900 resource hours must be outsourced. Because of internal
policies, all providers must comprehend the requirements. Which action should the project
manager take to ensure this?
- CORRECT ANSWER Conduct a bidder conference with the providers.
When delivering project outputs, the project team should consider answers to several
questions. Select three questions that are relevant to considering how and when to deliver
project outputs:
- CORRECT ANSWER Will the outputs be delivered in a new or existing business
environment? , Will the outputs result in the decommissioning or removing of old systems,
processes, or materials? , What needs to be done to ensure training and knowledge transfer is
complete or satisfactory?
As a project manager of an agile team, you are working on a project to roll out a new
Enterprise Resource Planning software organization-wide. Each department will have separate
"Go Live" dates and your first Go Live is next week. Your team has identified a few
impediments that threaten the start date of the Go Live if they are not dealt with. As they bring
these impediments to the attention of the rest of the team, what is the best way to track and
monitor the impediments until they are overcome?
- CORRECT ANSWER Use information radiators in co-located areas or software tools for full
visibility