QUESTIONS AND ANSWERS
A project manager is having difficulty obtaining consistent input from stakeholders and
needs their input to identify strategic and operational assumptions and constraints. How
can the project manager improve stakeholder input?
- CORRECT ANSWER Make use of effective facilitation techniques
While initiating a project that will impact seven different long-term client companies, you
realize the client companies have different ideas of what project success should look
like. To get them all on the same page you invite them to a meeting to gain agreement
before moving forward. What questions should you focus on clarifying with this group?
- CORRECT ANSWER What are the constraints, assumptions, and risks associated
with this project?
Align the terms below with the appropriate definition for impediments, obstacles, and
blockers:
- CORRECT ANSWER Impediment => Situations, conditions, and actions that slow
down or hinder progress
Obstacle => Barriers that should be able to be moved, avoided, or overcome with some
effort or strategy, Blocker => Events or conditions that cause stoppages in the work or
any further advancement
A project needs a specialized resource. A resource that fits the needs of the project is
identified, and can work onsite, but lives in another country. The visa process was
expected to take weeks but is now taking months. What should the project manager do?
- CORRECT ANSWER Request that the resource work virtually.
Your organization has just promoted three internal resources into project manager roles
due to the workload on current project managers. Due to their lack of experience, your
PMO has asked that you take the lead in onboarding, coaching, and mentoring these
new project managers. During a training session you are reviewing project documents
that are required by your PMO for each project. You are explaining the purpose and use
of each document. One of the new project managers asks when you need to create the
lessons learned register. She says that her previous project managers just created
those at the end of the project as they were finalizing the project and gaining final
closure approval. What is the best response to this question?
- CORRECT ANSWER While many project managers wait until the end of the project to
capture lessons learned, the lessons learned register should be created at the
beginning of the project and used to capture lessons learned throughout the project