Questions and Answers with Complete
Solutions
A _____ table lists resources and a schedule of when they are required. - ANSWER
loading
A brief daily meeting to plan the next 24 hours is a - ANSWER scrum
A chart showing the remaining backlog work is called - ANSWER burndown
A measurement process that determines the project goals and then the degree to which
the actual performance lives up to these goals is - ANSWER gap analysis
A meeting held to evaluate the previous cycle is called - ANSWER retrospective
A required delay between activities is called - ANSWER lag
A time-phased network used in project management is a - ANSWER Gantt chart
A tracking Gantt chart does not show - ANSWER the reason a task's schedule has
slipped
Accelerating a project must focus on - ANSWER critical path tasks
Accelerating the completion of a project is called - ANSWER crashing
Another name for resource leveling is - ANSWER smoothing
Decisions how to accelerate a project can be directly linked to - ANSWER cost
considerations
Dummy variables are used in what kind of network diagramming method?
a. AON
b. Gantt charts
c. AOA
d. OBS - ANSWER c. AOA
Earned value management jointly considers the impact of - ANSWER time, cost,
performance
If resources are assigned beyond the maximum level, then - ANSWER they are
overallocated
Interrupting work on a task and resuming it later is referred to as - ANSWER splitting