Answers with Complete Solution
1. Which statement describes best the purpose of the communications management
plan?70
a. The project management plan is a subsidiary document of the overall
communications management plan.
b. The communications management plan describes rules of behavior and respect for
communications in cross-cultural teams.
c. The communications management plan describes the information delivery needs
including format and level of detail.
d. The communications management plan focuses on the use of communications
technologies by the project management team - ANSWER C
1. While executing a project, you sense a slightly negative attitude in your team. Which
type of document do you now need, among others, to better understand and then be
able to improve the situation?74
a. Project charter
b. Team performance assessments
c. Cost baseline
d. Statement of work - ANSWER B
1. You identified a technical risk in your project and assigned a contingency for that.
Planning contingency reserves is part of which risk response strategy?77
a. Active risk mitigation
b. Passive risk avoidance
c. Passive risk acceptance
d. Active risk acceptance - ANSWER D
1. Which concept of locating team members can help them best to enhance their
performance as a team?78
a. Co-location
b. Cross-functional dispersion
c. Virtual e-teams
d. Global team dispersion - ANSWER A
1. What is least important when it comes to archiving project records?
a. A well-designed records management system
b. Integration of the archive with business software
c. Updated records reflecting final results
d. Easy availability of information for future use - ANSWER B
1. Your project, run for a customer, is coming to an end. The customer has been
contractually granted a three years warranty period for the product of the project. What
should you do first?
a. Hand all relevant documentation over to the organizational unit responsible for
handling the warranty.
, Proj Management 7 Questions and
Answers with Complete Solution
b. There is no additional work to be done. The contract should describe all processes in
sufficient detail.
c. Changes on the product can affect warranty clauses. Ensure that these clauses are
aligned with the final specifications.
d. According to many legislations, you cannot formally close a project before the end of
the warranty period. - ANSWER C
1. Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and
an SPI of 1.25. What is a plausible explanation for that?92
a. The project was terminated early. At that time, it was over budget and ahead of
schedule.
b. The project has produced additional deliverables which were originally not required.
c. The project has evidently been finished under budget and behind of schedule.
d. The project has evidently been finished over budget and ahead of schedule. -
ANSWER A
1. Which is not a goal in both project management and quality management?
a. Prevention over inspection
b. Customer satisfaction
c. Management responsibility
d. Triple constraint - ANSWER D
1. When finishing a project, which factors that influence customer satisfaction the most
should you be aware of? 106
a. Attractive price of the project and low running costs of the product
b. Friendly project manager and effective after-project service
c. Efficiency of the project and skills of the project manager
d. Conformance to requirements of the project and fitness for use of the deliverables -
ANSWER D
1. You finished your project for a customer to implement a business software solution.
All deliverables have been handed over and are already in use by the company. There
is a minor last payment to be made by the customer on contract closure. You believe
that it is now getting time to finally close the contract with the customer and then
administratively close down the project. You approached the customer this morning and
found that they are reluctant to finally close the contract. But you do not exactly
understand why. What should you not do?110
a. Update all documents related to the project and the product so that they reflect the
final specifications and the status of both the project and the product. Organize them in
a fashion for easy access.
b. Focus on your next project and leave the customer the time to get familiar with the
software. They will come back to you anyway after some weeks to terminate the
contract and make the last payment.